Skip to main content

First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of tra
April 4, 2016 Read time: 4 mins
First span of the north approach viaduct showing the north abutment. Photo: David Hunter
The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of traffic uses the new bridge.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the 6126 Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.
Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.

"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six-lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

Meanwhile, Total Plant Hire, based in Manchester, has hired out two new Doosan DA30 30tonne articulated dump trucks (ADTs) fitted with high flotation tyres for the project.

Like all 695 Doosan ADTs, the DA30 model features an articulation hinge behind the turning ring to provide equal weight distribution to the front axle even during maximum steer articulation. This together with a free-swinging rear tandem bogie ensures equal distribution of weight to each wheel and delivers permanent six-wheel contact and drive for equal power distribution and excellent performance on difficult terrain.
The specially shaped body and sloping frame on the DA30 offers a low centre of gravity and perfect weight distribution. The Doosan machines purchase by Total Plant Hire have been equipped with high flotation tyres to further help traction in the tough working conditions.

A temporary trestle bridge has been built as an access platform for workers build the new structures in the river. Accessed from the trestle bridge, temporary cofferdams have been built to enable foundations to be laid for the three pylons that will support the main bridge. The Doosan DA30 ADTs are removing earth excavated from the cofferdams and from others across the site.

The Doosan DA30 ADTs are also being for construction of supporting piers for the elevated approach viaducts, which cross the Manchester Ship Canal and the St Helens Canal. Each approach viaduct is supported by a number of supporting, there being 20 in total. These will march across the salt marsh on either side of the estuary.

For more information on companies in this article

Related Content

  • Mixing recycled and fresh asphalt reduces costs
    February 14, 2012
    An innovative asphalt plant is allowing the use of recycled materials and achieving major cost benefits - Mike Woof reports. UK construction firm FM Conway is seeing the benefit of the €11.5 million (£10 million) it has invested in its asphalt production facilities at Erith in Kent, close to UK capital London, since buying the site in 2005. The biggest single investment in the facility has been a new Benninghoven asphalt plant, which was commissioned in June 2010 and is now the core of the Erith operation.
  • AEC’s Model 6048 Bridge Deck Finisher in demand in Canada
    June 24, 2013
    Allen Engineering Corporation (AEC) recently delivered a Model 6048 Bridge Deck Finisher to PCR Contractors to be used on the 11km-long Rt. Hon. Herb Gray Parkway project in Canada. The US$1.4 billion highway infrastructure project is under construction in the Ontario municipalities of Windsor, LaSalle and Tecumseh. The Rt. Hon. Herb Gray Parkway will carry car and truck traffic from Hwy 401 in Canada to a new crossing across the Detroit River to I-75 in Michigan. The works will improve traffic flow at Cana
  • Highway project in Texas required demolition equipment
    May 1, 2018
    A contractor in Texas has used equipment from Brokk to help out with a tricky highway project. Upgrading work has been carried out on a 6.4km-long stretch of I-35 in San Antonio between Loop 410 NE and Loop 410 S. This stretch of the route was carrying around 185,000 vehicles/day and was suffering increasing levels of congestion at peak periods. Travel times lengthened by 65% during rush hour, while ramps on opposite sides of the interstate caused additional congestion and safety issues. In one section, t
  • Crane lifts in bridge structure in Germany
    December 14, 2015
    A Terex crawler crane has been used to lift out a concrete bridge in the German town of Zweibrücken. The work was carried out shortly after the Terex Superlift 3800 lattice boom crawler crane had been supplied to Trier-based specialist Steil. The crane hire firm already had four Terex crawler cranes in its fleet with this new arrival bringing the number to five. The machine had a particularly short journey to make to the job site as it had just been manufacturerd at the Terex facility located in Zweibrü