First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of tra
April 4, 2016 Read time: 4 mins
First span of the north approach viaduct showing the north abutment. Photo: David Hunter
The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of traffic uses the new bridge.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the 6126 Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.
Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.

"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six-lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

Meanwhile, Total Plant Hire, based in Manchester, has hired out two new Doosan DA30 30tonne articulated dump trucks (ADTs) fitted with high flotation tyres for the project.

Like all 695 Doosan ADTs, the DA30 model features an articulation hinge behind the turning ring to provide equal weight distribution to the front axle even during maximum steer articulation. This together with a free-swinging rear tandem bogie ensures equal distribution of weight to each wheel and delivers permanent six-wheel contact and drive for equal power distribution and excellent performance on difficult terrain.
The specially shaped body and sloping frame on the DA30 offers a low centre of gravity and perfect weight distribution. The Doosan machines purchase by Total Plant Hire have been equipped with high flotation tyres to further help traction in the tough working conditions.

A temporary trestle bridge has been built as an access platform for workers build the new structures in the river. Accessed from the trestle bridge, temporary cofferdams have been built to enable foundations to be laid for the three pylons that will support the main bridge. The Doosan DA30 ADTs are removing earth excavated from the cofferdams and from others across the site.

The Doosan DA30 ADTs are also being for construction of supporting piers for the elevated approach viaducts, which cross the Manchester Ship Canal and the St Helens Canal. Each approach viaduct is supported by a number of supporting, there being 20 in total. These will march across the salt marsh on either side of the estuary.

For more information on companies in this article

Related Content

  • FG among the first for Cat 966K
    November 30, 2012
    Fergusson Group (FG), the Scottish-based solid fuel import, export and distribution business, has assembled the largest Cat 966K wheeled loader fleet in the UK. The company’s six 966K machines are part of a €2.53million plus supply deal with Finning UK and Ireland. FG has also added a Cat 725 ADT, Cat 320DL excavator and Cat 226b skid steer loader to its fleet. Launched in 2012, the 966K wheeled loaders combine the Cat C9.3 ACERT Stage IIIB compliant engine with new performance series buckets. Finning clai
  • Hillhead promises industry showcase
    June 12, 2012
    Hillhead 2012, the three-day biennial flagship event for the quarrying, recycling and heavy construction industries, is set to be a sell-out. Guy Woodford looks at what a number of major companies will be exhibiting during the show being held next month at Buxton Quarry in Derbyshire With 400 exhibitors already confirmed Hillhead 2012, taking place 19-21 June, is set to draw bumper crowds and provide crucial new business opportunities for companies involved in quarrying, recycling and heavy construction. Ca
  • How bitumen technology solutions are solving paving problems around the world
    March 2, 2017
    This month we hear how additives can bring RAP back from the dead and fight the ravages of salt damage, how pellets reach parts that PMB can’t and how Shell and WeedsWest are expanding their respective businesses - Kristina Smith writes
  • Terex Trucks scoring order in South Africa
    May 11, 2018
    Terex Trucks is building its market share in South Africa through its partnership with Babcock International The Generation 10 articulated hauler is now developing sales in the Southern Africa region, while the rigid haulers such as the top-of-the-range TR100 are also said to be proving popular. With a series of investments, Terex Trucks has been working together with Babcock to strengthen the perception of its articulated and rigid haulers, through factory visits to the manufacturer’s headquarters in Mo