First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of tra
April 4, 2016 Read time: 4 mins
First span of the north approach viaduct showing the north abutment. Photo: David Hunter
The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of traffic uses the new bridge.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the 6126 Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.
Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.

"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six-lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

Meanwhile, Total Plant Hire, based in Manchester, has hired out two new Doosan DA30 30tonne articulated dump trucks (ADTs) fitted with high flotation tyres for the project.

Like all 695 Doosan ADTs, the DA30 model features an articulation hinge behind the turning ring to provide equal weight distribution to the front axle even during maximum steer articulation. This together with a free-swinging rear tandem bogie ensures equal distribution of weight to each wheel and delivers permanent six-wheel contact and drive for equal power distribution and excellent performance on difficult terrain.
The specially shaped body and sloping frame on the DA30 offers a low centre of gravity and perfect weight distribution. The Doosan machines purchase by Total Plant Hire have been equipped with high flotation tyres to further help traction in the tough working conditions.

A temporary trestle bridge has been built as an access platform for workers build the new structures in the river. Accessed from the trestle bridge, temporary cofferdams have been built to enable foundations to be laid for the three pylons that will support the main bridge. The Doosan DA30 ADTs are removing earth excavated from the cofferdams and from others across the site.

The Doosan DA30 ADTs are also being for construction of supporting piers for the elevated approach viaducts, which cross the Manchester Ship Canal and the St Helens Canal. Each approach viaduct is supported by a number of supporting, there being 20 in total. These will march across the salt marsh on either side of the estuary.

For more information on companies in this article

Related Content

  • JCCBI says US$300m for demolishing Montreal’s old Champlain Bridge
    April 11, 2017
    Tearing down the old steel truss cantilever Champlain Bridge in Montreal could cost around US$300 million, according to preliminary estimates by a federal government agency. Also, until the nearby new Champlain Bridge is finished, it will cost US$93 million annually to maintain the old one, according to Jacques Cartier and Champlain Bridges Incorporated (JCCBI), the federal Canadian agency that oversees several major road infrastructure assets in the city. Dismantling will start in 2019 at the earliest and
  • Saudi Arabian capital Riyadh benefiting from major transport investment
    September 9, 2013
    Saudi Arabia is undergoing a series of upgrades to its transport network in a bid to improve Traffic flow rates and boost safety - Mike Woof reports. The massive growth in the use of motor transport worldwide since the start of the 20th century has transformed every country on the planet. But perhaps no country has changed more dramatically than Saudi Arabia, the world’s leading oil producer. At the start of the 20th century Saudi Arabia’s population was small and the country had few industries while it is
  • Athabasca’s Hwy 813 bridge to be replaced
    May 16, 2022
    The new bridge over the Athabasca River in the Canadian province of Alberta will include two 3.7m-wide lanes with 1.8m-wide shoulders on either side as well as a pedestrian sidewalk.
  • Expansion of the Panama Canal
    February 24, 2012
    In Panama, a ten-year US$5 billion project is underway to double the capacity of the Panama Canal Since its completion in 1914 the Panama canal has allowed shipping to cross the 80km wide isthmus at the narrowest part of the Americas. Belgian company Dredging International's D'Artagnan, a self-propelled heavy-duty cutter suction dredger, arrived at the canal, and the latest addition to the Panama Canal Authority's (ACP) expansion dredging fleet then made its way to the Pacific entrance, where it will expa