First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of tra
April 4, 2016 Read time: 4 mins
First span of the north approach viaduct showing the north abutment. Photo: David Hunter
The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of traffic uses the new bridge.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the 6126 Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.
Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.

"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six-lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

Meanwhile, Total Plant Hire, based in Manchester, has hired out two new Doosan DA30 30tonne articulated dump trucks (ADTs) fitted with high flotation tyres for the project.

Like all 695 Doosan ADTs, the DA30 model features an articulation hinge behind the turning ring to provide equal weight distribution to the front axle even during maximum steer articulation. This together with a free-swinging rear tandem bogie ensures equal distribution of weight to each wheel and delivers permanent six-wheel contact and drive for equal power distribution and excellent performance on difficult terrain.
The specially shaped body and sloping frame on the DA30 offers a low centre of gravity and perfect weight distribution. The Doosan machines purchase by Total Plant Hire have been equipped with high flotation tyres to further help traction in the tough working conditions.

A temporary trestle bridge has been built as an access platform for workers build the new structures in the river. Accessed from the trestle bridge, temporary cofferdams have been built to enable foundations to be laid for the three pylons that will support the main bridge. The Doosan DA30 ADTs are removing earth excavated from the cofferdams and from others across the site.

The Doosan DA30 ADTs are also being for construction of supporting piers for the elevated approach viaducts, which cross the Manchester Ship Canal and the St Helens Canal. Each approach viaduct is supported by a number of supporting, there being 20 in total. These will march across the salt marsh on either side of the estuary.

For more information on companies in this article

Related Content

  • Terex's new TA300 articulated truck which joins the company's new product family of ADTs
    February 6, 2012
    Terex has launched its new TA300 articulated truck which joins the company's new product family of ADTs. Terex claims that the TA300, which replaces the TA30 model launched in 2002, is the only hauler in 30tonne market that has fully independent front suspension (IFS) as standard. The model joins the TA350 (previously TA35) and TA400 (TA40), launched in September, 2009. and the TA250 being launched in April.
  • Building an airport for St Helena
    August 29, 2013
    The remote South Atlantic island of Saint Helena will shortly benefit from the construction of a new airport as well as access roads and supporting infrastructure. This is the biggest construction project in the history of the island, which lies nearly 2,000km off the coast of Africa. The airport is expected to boost economic development for the island’s 4,000 residents with an estimated 20,000 people a year forecasted to visit this highly remote, 122km2 equatorial volcanic outcrop. At present the islan
  • Canadian PM Trudeau warned of costs rises for Gordie Howe Bridge
    January 11, 2016
    A devaluing Canadian dollar has pushed up the cost for building a signature Windsor-Detroit bridge by around US$2.5 billion, according to Canadian media reports. The increase more than doubles what was believed needed by the Canadian government to construct the Gordie Howe Bridge, named after a Canadian ice hockey player who played most of his career for the Detroit Red Wings. The toll bridge, to be built under a public private partnership, will link the US city of Detroit, in the state of Michigan, w
  • Busy UK motorway junction demolished in tight time frame – Mark Anthony reports
    October 18, 2012
    Military-style planning and overwhelming demolition firepower ensured that Armac Group avoided financial penalties and the wrath of drivers on one of the UK’s busiest motorway intersections. Demolition & Dismantling reports. 6 January is traditionally known for the visit of the three wise men to Bethlehem. However, on 6 January 2012, three wise demolition engineers from Armac Group was tasked with dismantling the monumental structure known as Catthorpe Viaduct: the main overbridge of the M6/M1/A14 interc