Cold road reclamation in South Africa

Raubex Construction’s new Cat RM500 rotary mixer is proving its worth on a road reclamation work on a South African highway Part of an extensive motorway network some 185km long, South Africa’s ongoing Gauteng Freeway Improvement Project (GIFP) is creating a modern, world-class toll route system. The new road will provide major impetus to socio-economic growth in the country’s most populous and commercially active region. Being built in stages by the South African National Roads Authority (SANRAL), these r
July 18, 2012 Read time: 5 mins
A new Cat RM500 rotary mixer was an early contributor on the jobsite

Raubex Construction’s new CAT's RM500 rotary mixer is proving its worth on a road reclamation work on a South African highway

Part of an extensive motorway network some 185km long, South Africa’s ongoing Gauteng Freeway Improvement Project (GIFP) is creating a modern, world-class toll route system. The new road will provide major impetus to socio-economic growth in the country’s most populous and commercially active region.

Being built in stages by the South African National Roads Authority (SANRAL), these roads radiate outward in all directions from Johannesburg and Pretoria’s industrial and residential centres.

Some sections of the road have already been completed, and the results are impressive. Congestion has been replaced by free-flowing traffic, an improvement crucial to the area’s business interests.

National Route 12 (N12) is one of SANRAL’s strategic priorities next in line for improvement. Civil engineering contractor 3038 Raubex Construction has been hired to overhaul a 10km stretch known as Section 19. The scope of the work is challenging, and expected to last more than 30 months.

The existing N12 two-lane road will be replaced by three major new interchanges, successive bridge widenings and three east-bound and three west-bound lanes, which will be placed in an existing median, and a central concrete barrier installed for safety.

Section 19 includes the main access point to Gauteng’s West Rand region, which flows to the agricultural and mining heartland of Mpumalanga Province.

Managing high traffic densities as the roads are realigned is among the challenges.

The durability of the well-travelled road starts with the creation of the base. The N12 design calls for an emulsion and cement stabilisation mix for the sub-base layers. That work is already under way.

“What makes the N12 project particularly noteworthy is that all materials will be worked in-situ or sourced from cuttings that will make way for the new lanes and interchanges along the route,” explained Raubex Construction’s Johan van der Merwe.

“Achieving this requires very complex planning to meet incremental timeframes.”

Some 74 earthmoving machines will be deployed on the N12 site at some time during the project, a high percentage of which are 178 Caterpillar machines supplied and supported by Southern African Cat Dealer, Barloworld Equipment.

A new Cat RM500 rotary mixer was an early contributor on the jobsite. The machine handled full-depth reclamation and soil stabilisation for both the new and existing lanes.

Barloworld Equipment’s product manager, Johan Hartman, explained that the Cat RM500 has an operating weight of 28,145kg and is driven by a Cat C15 ACERT engine generating a gross power output of 403kW. This compares with the Cat RM300 operating weight of 24,454kg and gross power delivery of 261kW via its Cat C11 engine. Width of cut on both models is the same at 2,438mm, while the maximum cutting depth is 457mm.

Unlike the RM300 unit, which has a single water pump for optimum moisture content delivery, the RM500 design incorporates both a water and an emulsion pump that are simultaneously monitored in the cab via two separate flow meters. The RM500 pushed two tankers, one carrying 18,000litres of emulsion and the other 18,000litres of water, for the sub-base phase. The emulsion ratio was between 2-3% and cement around 1.5-2%.

With the RM500, Raubex was able to reclaim and stabilise the 300mm sub-base in one pass.

The equipment team on the ETB section will comprise the Cat RM500, the latest generation Cat 140K motor grader, plus Cat CS76 single drum 20tonne vibratory rollers.

In the 300mm sub-base layer, the RM500’s universal rotor-equipped with its 200 carbide-tipped bits arranged in a chevron pattern-came into play in reworking these dense in-situ materials, providing a very high level of material pulverisation and gradation. A three-position mode switch enabled the rotor depth to be controlled manually or automatically to a preset cutting depth to ensure that the engineering design was precisely met.

Most often on the job the machine cut at a depth of 45cm, including a 7cm asphalt surface.

The RM500 mixing chamber features a heavy-duty hood with a large volume capacity to handle deep mixing, and this ensures exact depth control, proper sizing and thorough blending of reclaimed materials.

The production requirements on Section 19 are substantial. Raubex’s RM500 was deployed for the sub-base component, amounting to 135,000m3, while the selected 300mm layer comprised some 102,000m3.

Additionally, the new highway construction will require some 9 million litres of emulsion, 5,000tonnes of cement, 114,000tonnes of BTB, plus 530,000m2 of 35mm AE2 asphalt premix and the equivalent for the 18mm ultra-thin friction course (UTFC) overlay for the final riding surface.

Black-topping will be carried out by Raubex division, Roadmac Surfacing.

The purchase of sub-grade materials from the crushing plant was not required because the machine was able to turn the reclaimed gravel into sub-base material.

“Efficient use of materials and machines will be interdependent on this contract and we have invested in the best possible technologies to meet our completion targets as we steadily transform Section 19 into a multi-lane world-class highway,” van der Merwe added.

For more information on companies in this article

Related Content

  • Road recycling saves time and costs, reduces emissions
    February 13, 2012
    Stabilisers bring recycling improvements to roads in the UK and Armenia. The local road authorities near the UK city of Bath have saved nearly €250,500 on the cost of repairing a 400m long section of the B3110 Midford Road. This saving has been achieved by opting to recycle and strengthen in-situ the existing surface, instead of using conventional full depth pavement reconstruction.
  • Key Botswana road network gets an upgrade
    June 30, 2014
    Representing an investment of around US$113 million, Botswana’s A1 national road between Tonota and Francistown is undergoing a major upgrade This single-lane section is being progressively transformed into a north- and southbound dual carriageway, crossing four existing river bridges along the way. A strategically important transportation route for both Botswana and the southern African region, the A1 passes through Francistown, the nation’s second largest city, heading northwards to end at the Zimbabwe b
  • Success of hot mix asphalt road recycling
    March 7, 2012
    Russian construction firm Kamdorstroy has carried out a successful demonstration of recycling techniques to over 60 highway officials, academics and contractors from all over the CIS states. The demonstration was carried out in co-operation with the Russian Federal Highway and Tatarstan Highway authorities and involved milling, recycling and overlaying a road with hot mix asphalt. The work was carried out on a 7.5m wide roadway with 3.8m wide lanes (with an overlap) using machinery and techniques new to Rus
  • Recycling machines have helped add new lanes to an Italian highway
    May 30, 2013
    The use of recycling and stabilisation equipment has played a key role in adding new lanes to a congested Italian highway. Running from Bologna to Taranto, the A14 Autostrade has seen a major increase in traffic volumes for several years. Data shows that traffic has increased around 4% year on year with some 110,000 vehicles using the highway/day. The traffic growth trend looks set to continue and this resulted in the Italian Government opting to upgrade and widen the route.