Clever electric solution for embankment stabilisation

A highly innovative solution for road embankment stabilisation has helped save costs by up to 30% over conventional techniques. Balfour Beatty Mott MacDonald has used electrical current to stabilise embankments on a busy UK dual carriageway, avoiding disruption to motorists, cutting carbon by 40% and costs by 30%, and producing zero waste When slope failure was detected on embankments carrying the popular A21 dual carriageway, Balfour Beatty Mott MacDonald pioneered a novel technique to tackle the prob
August 28, 2013 Read time: 3 mins
The positively charged anodes were driven into the slope and negatively charged cathodes are installed into holes formed using a continuous flight auger, with the cathodes allowing drainage

A highly innovative solution for road embankment stabilisation has helped save costs by up to 30% over conventional techniques. Balfour Beatty Mott MacDonald has used electrical current to stabilise embankments on a busy UK dual carriageway, avoiding disruption to motorists, cutting carbon by 40% and costs by 30%, and producing zero waste

When slope failure was detected on embankments carrying the popular A21 dual carriageway, 1530 Balfour Beatty Mott MacDonald pioneered a novel technique to tackle the problem. This solution at Stocks Green avoided lane closure, preventing traffic disruption on the busy road, and also cut costs.

The earth embankment had been constructed with sides that were too steep and combined with poor drainage, this was causing the slopes to shear and slump. “Progressive failure would have undermined the safety barrier,” said Michael Tandy, Balfour Beatty Mott MacDonald geotechnical engineer.

Slope failure is normally tackled by replacing earth with granular material that is freer draining and better withstands loading, mixing lime into the embankment to stiffen and strengthen it, installing soil nails, or building retaining walls. All involve removing vegetation and closing traffic lanes. “The A21 is a major commuter route, so restricting the width of the road would have resulted in major congestion,” Tandy said.

Instead the firm opted to try a technique combining electro-osmosis with soil nailing and drainage, patented by its supply chain partner Electrokinetic. More than 200 years ago, it was observed that when an electrical current was passed through fine-grained material, it drew water along with it. Electrokinetic has harnessed this principle, known as, electrokinetic geosynthetics (EKG).

The company has developed a lightweight, mobile, track-mounted drilling and nailing rig, which was used to install 195 perforated steel tubes into the ground. Driven anodes were angled downward, acting like nails to hold material in place, while cathodes were inserted into pre-bored holes, sloping upward to act as drains to bring water from deep within the embankment to the surface.

Using a mobile generator, current was passed from anodes to cathodes to draw water out of the soil structure, consolidating it. “This method has been used in mining, in construction of dams and docks and on the 1211 London Underground,” Michael explains. “This was the first time the technology had been applied to a major road in the UK.”
After six weeks the drainage phase was complete and the electricity shut off. To convert the anodes into permanent soil nails, grout was injected down the tubes and forced out, through the perforations, into the surrounding ground, locking the nails firmly into the soil matrix. The drains remain permanently in place.

Work was carried out from the foot of the embankment, meaning no lane closures were required. “The approach taken by Balfour Beatty Mott MacDonald meant personnel weren’t exposed to risk from passing vehicles,” Tandy said.

The scheme has won two industry awards for innovation and sustainability. “The technology worked so well that the 2309 Highways Agency has already awarded contracts to use it elsewhere on the highways network,” Tandy said.

For more information on companies in this article

Related Content

  • Controversial £2 billion Stonehenge bypass project halted
    July 30, 2024
    The UK's controversial £2 billion Stonehenge bypass project has been halted, prompting relief amongst environmentalists and historians who opposed the construction work.
  • El Sillar – Bolivia’s challenging road project
    February 6, 2020
    Construction of Bolivia’s El Sillar highway, the country’s most complicated road project – Mauro Nogarin reports
  • Stabilising performance from reclaimers
    June 18, 2012
    New stabiliser/reclaimer models are coming to market – Mike Woof reports With road recycling becoming a more widely used approach, several key manufacturers are meeting demands for higher performance. From BOMAG comes the latest version of the MPH 125 soil stabiliser/recycler, which is now available with the new FLEXMIX technology. This package is said to set new standards in mix quality for all applications, with an optional change in the mix function that broadens the range of options available to the
  • Foiled by foliage from Biotecture
    June 27, 2022
    Richard Sabin, managing director of Biotecture*, details how living walls provide an innovative solution for reducing air pollution and improve air quality along congested urban highways.