Clever electric solution for embankment stabilisation

A highly innovative solution for road embankment stabilisation has helped save costs by up to 30% over conventional techniques. Balfour Beatty Mott MacDonald has used electrical current to stabilise embankments on a busy UK dual carriageway, avoiding disruption to motorists, cutting carbon by 40% and costs by 30%, and producing zero waste When slope failure was detected on embankments carrying the popular A21 dual carriageway, Balfour Beatty Mott MacDonald pioneered a novel technique to tackle the prob
August 28, 2013 Read time: 3 mins
The positively charged anodes were driven into the slope and negatively charged cathodes are installed into holes formed using a continuous flight auger, with the cathodes allowing drainage

A highly innovative solution for road embankment stabilisation has helped save costs by up to 30% over conventional techniques. Balfour Beatty Mott MacDonald has used electrical current to stabilise embankments on a busy UK dual carriageway, avoiding disruption to motorists, cutting carbon by 40% and costs by 30%, and producing zero waste

When slope failure was detected on embankments carrying the popular A21 dual carriageway, 1530 Balfour Beatty Mott MacDonald pioneered a novel technique to tackle the problem. This solution at Stocks Green avoided lane closure, preventing traffic disruption on the busy road, and also cut costs.

The earth embankment had been constructed with sides that were too steep and combined with poor drainage, this was causing the slopes to shear and slump. “Progressive failure would have undermined the safety barrier,” said Michael Tandy, Balfour Beatty Mott MacDonald geotechnical engineer.

Slope failure is normally tackled by replacing earth with granular material that is freer draining and better withstands loading, mixing lime into the embankment to stiffen and strengthen it, installing soil nails, or building retaining walls. All involve removing vegetation and closing traffic lanes. “The A21 is a major commuter route, so restricting the width of the road would have resulted in major congestion,” Tandy said.

Instead the firm opted to try a technique combining electro-osmosis with soil nailing and drainage, patented by its supply chain partner Electrokinetic. More than 200 years ago, it was observed that when an electrical current was passed through fine-grained material, it drew water along with it. Electrokinetic has harnessed this principle, known as, electrokinetic geosynthetics (EKG).

The company has developed a lightweight, mobile, track-mounted drilling and nailing rig, which was used to install 195 perforated steel tubes into the ground. Driven anodes were angled downward, acting like nails to hold material in place, while cathodes were inserted into pre-bored holes, sloping upward to act as drains to bring water from deep within the embankment to the surface.

Using a mobile generator, current was passed from anodes to cathodes to draw water out of the soil structure, consolidating it. “This method has been used in mining, in construction of dams and docks and on the 1211 London Underground,” Michael explains. “This was the first time the technology had been applied to a major road in the UK.”
After six weeks the drainage phase was complete and the electricity shut off. To convert the anodes into permanent soil nails, grout was injected down the tubes and forced out, through the perforations, into the surrounding ground, locking the nails firmly into the soil matrix. The drains remain permanently in place.

Work was carried out from the foot of the embankment, meaning no lane closures were required. “The approach taken by Balfour Beatty Mott MacDonald meant personnel weren’t exposed to risk from passing vehicles,” Tandy said.

The scheme has won two industry awards for innovation and sustainability. “The technology worked so well that the 2309 Highways Agency has already awarded contracts to use it elsewhere on the highways network,” Tandy said.

For more information on companies in this article

Related Content

  • Cold recycling helps rebuild of Brazil’s Ayrton Senna highway
    September 28, 2015
    Brazil’s Ayrton Senna Highway has been rebuilt using cold recycling. Brazil’s SP-070 is also known as the Ayrton Senna Highway and is a major highway in the country, carrying heavy traffic volumes. For its rebuild, the time-saving, cost-efficient and eco-friendly benefits of the cold recycling process have been put to the test. The SP-070 provides a key transport link between São Paulo and Campos do Jordão, Vale do Paraíba and Rio de Janeiro, as well as being the main access route to Guarulhos Interna
  • Balfour Beatty Mott McDonald secure key H Agency contract
    June 15, 2012
    The Highways Agency has awarded the second of its new Asset Support Contracts to Balfour Beatty Mott MacDonald. The contract involves maintaining and improving the network of motorways and major ‘A’ roads in the North West. It will cover the Agency’s roads in Cheshire, Greater Manchester, Merseyside and south Lancashire and will go live from November 2012. Cumbria and the remainder of Lancashire are covered by a separate contract. The key contract will ensure motorways and major 'A' roads in the region co
  • Kosovo's award-winning green highway construction
    March 20, 2012
    A new highway is proving an economic lifeline for the tiny country of Kosovo – Mike Woof reports. Road projects in Europe rarely meet such widespread public approval and support as the new Route 7 highway being built in the new Balkan state of Kosovo. The first sections of the new road opened to traffic in November 2011, with locals turning out in large numbers to celebrate the event. The official opening was carried out by the country’s prime minister Hashim Thaçi, president Atifete Jahjaga, and members of
  • Welsh contractor enlists a ‘road warrior’ for stabilisation work in England
    September 28, 2015
    Groundworks contractor DCM Roadways, based in the southeast Wales town of Monmouth, has brought in an FAE MTM to ensure the best result possible for an access road project. DCM, which specialises in soil stabilisation and road recycling, is working on a solar project in the Forest of Dean area of Gloucestershire county, just across the border in England. The job is for the construction of around 1.2km of stabilised highway access roads.