Bulgaria: back on track?

Several important Bulgarian road projects are expected to gain momentum over the coming weeks, a welcome boost for a sector that has been beset by delays in the past. In mid-September, the National Road Infrastructure Agency (NRIA) announced that it would soon be declaring new tenders for the construction of two key road projects worth a total of US$94 million (approximately €68.8 million). One section will link the south-eastern city of Kardzhali to Podkova, near the Greek border: the second will connect t
July 23, 2012 Read time: 4 mins

The EC is taking a more supportive position, as Bulgaria attempts to put its road building programme back on track, writes Gordon Feller

Several important Bulgarian road projects are expected to gain momentum over the coming weeks, a welcome boost for a sector that has been beset by delays in the past. In mid-September, the National Road Infrastructure Agency (NRIA) announced that it would soon be declaring new tenders for the construction of two key road projects worth a total of US$94 million (approximately €68.8 million).

One section will link the south-eastern city of Kardzhali to Podkova, near the Greek border: the second will connect the Sofia ring road to the Hemus Highway, which runs from the capital to Varna, Bulgaria's second largest commercial centre on the Black Sea coast.

Both projects have been held up by funding irregularities, while the Kardzhali-Podkova road was the subject of some controversy as the original concession was allegedly awarded in breach of proper procedure.

Another major project, the Lyulin Motorway, a 19km stretch linking Sofia with the prospective Struma Motorway leading to the south-western border town of Kulata, and then to the Greek city of Thessaloniki, should also receive a boost soon.

The Transport Ministry, the NRIA (until recently the National Road Infrastructure Fund) and the 2465 European Commission (EC) are expected to reach a deal on tenders for technical support for the motorway's construction as we go to press.

This follows the news from July, when it was revealed that the contractor, Turkish firm 4148 Mapa-4144 Cengiz, had only completed 5% of the road, rather than the 40% scheduled for mid-2008. The project had been delayed by labour shortages and difficulties in obtaining visas for Turkish workers, and is now due for completion in May 2010.

Previous EU funding to the Lyulin project through the Instrument for Structural Policies for Pre-Accession (1118 ISPA) programme, which aims to develop transport infrastructure in countries joining the EU, had been suspended over doubts about adherence to procedural rules. Once a new settlement has been reached, the EC will decide whether to continue financing road projects under ISPA, with the announcement expected on 24 November 2008.

The EU had previously agreed to provide $163 million (€119.5 million) of the estimated $217 million (€160 million) cost of the Lyulin Motorway, which is considered vital to easing traffic pressures around Sofia and improving cross-continent transport links.

The Bulgarian capital lies at the confluence of three major pan-European transport corridors, key routes earmarked by European governments for development. These are corridors VIII (which runs from Durres on Albania's Adriatic coast to Varna, including Bulgaria's partially complete Trakia Motorway) and X and IV, from Central Europe to Istanbul and Thessaloniki, respectively.

Despite the expected fillip to Bulgaria's road building programme, the process of upgrading the country's creaking network is likely to be a slow and expensive one. The Struma Motorway, which is also only partially complete, is a crucial section of corridor IV, but is not expected to be finished until 2020. The road's cost has been estimated at $880 million (€645 million), but recent media reports suggest that it could run to $1.45 billion (€1 billion), partly due to additional environmental protection measures.

The government claimed in mid-September that it had made record progress in highway construction, with 100km of motorway and 4,000km of other roads completed in just three years.

Certainly, recent developments indicate that the authorities are pushing forward with road-building schemes despite the EC's suspension of a €519 million block of funding in July, the latest of a series of freezes affecting expenditure on transportation.

The government has allocated €260 million of the budget surplus to an "infrastructure package," which includes the continuation of work on the Trakia Motorway.

Prime Minister Sergei Stanishev has given notice that he is willing to dip further into the budget surplus, which totalled €2.18 billion in the first seven months of the year, in order to keep infrastructure developments on track. n

The government has allocated €260 million of the budget surplus to an "infrastructure package," which includes the continuation of work on the Trakia Motorway

For more information on companies in this article

Related Content

  • Bids in for next Bucharest A0 orbital work
    August 10, 2021
    The A0 orbital motorway will run about 100km around the Romanian capital.
  • JP Autoceste eyes 2020 as completion date for Bosnia’s Corridor 5c
    March 3, 2016
    Around two-thirds of the Corridor 5c motorway project is expected to be completed by 2020, according to the director of the Bosnian motorways company JP Autoceste. Jasmin Buco said that 120km out of 337km of the motorway are complete. The corridor section, to connect Budapest with Ploce port in Croatia, is taking the most time. He said that the cost of the remaining part of the motorway is expected to be around €2.81 billion.
  • Bulgaria will attract infrastructure investment
    July 5, 2012
    Key infrastructure projects look set to help revitalise Bulgaria’s economy. Concession packages for 10 infrastructure projects in the country could attract outside investment worth as much as €511.3 million. Bulgaria's Transport Ministry believes that the country could qualify for some €2 billion in EU funding for the development of transport corridors in the period from now until to the end of 2014.
  • Corridor 10 project in Serbia may be delayed
    April 2, 2013
    A series of challenges are now facing the project to construct Serbia’s key Corridor 10 highway. The EU has asked the Serbian Government for details of the priority plan and deadlines for the completion of the Corridor 10 highway. At present three sections of Corridor 10 are at risk, due to delays and financing issues. These are the Ciflik-Pirot stretch, the Bancarevo tunnel and the Vladicin Han section. According to Serbian roads company Koridori Srbije, the construction schedule will be set by the end of