Asphalt for an airport

A Lintec CSD2500B containerised asphalt mixing plant is playing a key role for the Yap Island airport rehabilitation project in Micronesia
September 12, 2023 Read time: 3 mins
The ease of transport of the containerised asphalt plant from Lintec & Linnhoff is a key benefit for operations on the remote islands

The 2km-long runway rehabilitation on Yap Island will require 26,000tonnes of hot mix asphalt and is set to be completed in 2024. The Lintec CSD2500B's containerised design is particularly suitable for working in such remote Pacific Islands due to its portability.

Contractor GPPC acquired a Lintec CSD2500B containerised asphalt mixing plant and has started work on the runway and taxiway rehabilitation project at Yap International Airport (YAP). The airport is located in the Yap Islands, also known as Wa’ab, in the Federated States of Micronesia. Located in the western Pacific Ocean almost 1,440km due east of the Philippines, the airport runway was due for improvement to support international connections to Guam and Palau.

The containerised design of the Lintec CSD range of asphalt mixing plants allows easy, low cost transportation making it suit project works, a feature that is valued amongst customers. The contractor has benefited from this features as the plant will eventually be moved and carry out other works across the remote Pacific Islands.

The airport rehabilitation project started in April 2022 and the plant was installed in January 2023, ready to begin repaving the 2km-long by 61m-wide runway with approximately 26,000tonnes of hot mix asphalt. After the job is completed around April 2024, the CSD2500B’s portability advantages will be valuable when the plant moves to nearby islands for the next project.

“There are several unique, major challenges that are present when working on remote islands,” said Jefferson Gayas, project manager, GPPC. “Getting hold of quality materials can be difficult, and equipment is often in short supply. It’s also rare for projects or consecutive jobs to take place on the same island so the ease with which the CSD2500B can be relocated makes that task much less of a headache.”

The 2km-long by 61m-wide airport runway on Yap Island will benefit from a new asphalt surface, with the material delivered from a Lintec & Linnhoff containerised plant
The 2km-long by 61m-wide airport runway on Yap Island will benefit from a new asphalt surface, with the material delivered from a Lintec & Linnhoff containerised plant

Island projects are typically smaller, which results in quicker completion schedules so the modular construction of the CSD asphalt mixing plant lends itself to rapid and convenient dismantling and installation. Built within ISO certified sea containers, thThe 2km-long by 61m-wide airport runway on Yap Island will benefit from a new asphalt surface, with the material delivered from a Lintec & Linnhoff containerised plant
is Lintec design can be efficiently and economically transported on land and sea. The internal components are also protected from salt ingress during sea transport, a vital consideration when the equipment is moved between Pacific Islands.  

Once delivered to the new jobsite, the rigid nature of the containers reduces plant setup cost. It removes the need for concrete foundations to be prepared due to their high stability on suitably compacted soil. Their enclosed structure also boosts security with a single, lockable main access door.

As an ideal choice for both small and big projects, the CSD2500B provides an output of up to 160tonnes/hour, in 2.5tone batches. Its double screen drum technology combines the heating and screening of aggregates in a single unit. This eliminates the need for a hot elevator and vibrating screens, greatly reducing fuel consumption and maintenance.

The Yap Islanders also have a long history as experienced sailors, aiding in the moving of the asphalt plant between the islands and over hundreds of kilometres, according to Lintec & Linnhoff.

For more information on companies in this article

Related Content

  • Papua New Guinea mends its bridges
    February 28, 2022
    Under the latest tranche of the Sustainable Highlands Highway Investment Programme, 45 of the estimated 71 bridges will be completely replaced.
  • The environmental high road with VIALOW
    May 11, 2021
    VIALOW uses a bitumen additive to enable asphalt manufacture at up to 40°C lower than standard mixes with no compromise in performance, according to CEMEX.
  • 18th IRF World Meeting & Exhibition Draws Global Stakeholders to Dubai
    January 20, 2022
    The 18th IRF World Meeting & Exhibition, a four-day global summit and technology showcase in Dubai, UAE, came to a close on November 10th, 2021. The culmination was a renewed call for consensus-building and knowledge partnerships in industry to address key sustainability and mobility challenges.
  • Colombia’s Toyo Tunnel project providing key link
    May 20, 2016
    Colombia’s Toyo Tunnel project will provide an important new link for the country, writes Mauro Nogarin. The new Toyo Tunnel project is of immense importance for Colombia, improving transportation and providing an important road link. The work is being carried out by the Antioquia to the Sea Consortium, which comprises of FCC Construction, Cass Builders and Company, Carlos Alberto Solarte and Estyma Studies and Handling. These firms are building the Toyo Tunnel project and the various access roads, with the