Commuter traffic in the Taipei Metropolitan Area is a major concern for the city’s town planners. In 2009, a decision was reached to widen National Freeway No. 1 between Wugu and Yangmei on a 42km section of freeway on the northern part of town. The lane-widening project saw the construction of two new viaducts built along each side of the freeway. From the onset, the project presented tremendous challenges owing to various factors, including limited space for construction; passing through a geologically
September 15, 2015 Read time: 3 mins
The Wu-Yang Viaduct took four years to complete but proved less costly to construct than first thought
National Freeway No 1 Widening Project

Commuter traffic in the Taipei Metropolitan Area is a major concern for the city’s town planners. In 2009, a decision was reached to widen National Freeway No. 1 between Wugu and Yangmei on a 42km section of freeway on the northern part of town. The lane-widening project saw the construction of two new viaducts built along each side of the freeway.

From the onset, the project presented tremendous challenges owing to various factors, including limited space for construction; passing through a geologically sensitive area; maintaining traffic on a busy section of freeway with 250,000 vehicles per day; and implementing a complex technical design. New and innovative construction methods were introduced by project designer CECI Engineering Consultants, Inc (CECI) aimed at fast-tracking the project’s design and construction activities by optimising the allocation of construction resources and schedules during all stages of work.

CECI was commissioned to carry out design and construction supervision services for both the northern and middle segments of the project with a continuous running length of 28km, and from the start, undertook a design emphasising speed, value and innovation without sacrificing quality and safety.

Notable features of the project included pioneering construction processes, as illustrated by the utilisation of a new horizontal rotation method aimed at shortening construction time and avoiding deploying piers or supporting structures that would otherwise have disrupted existing traffic. To avoid impeding the traffic flow, overpasses were designed for the viaduct to cross the freeway and merge into a double-deck structure.
Throughout the project environmentally protective measures were adopted ranging from tree relocation and transplantation, to the designation of non-disturbance zones aimed at preserving the habitats, ground soil and wetlands. Noise reduction measures, such as low noise expansion joints and infiltration pavement, were also adopted to maximise performance of the viaduct. Finally, an “F type” double-deck structure merging the two viaducts along both sides of the freeway together allowing both decks to use the same supporting columns was selected in order to avoid a geologically sensitive area.

After four years of intensive efforts, the entire viaduct was opened to traffic in April 2013 at a total cost of US $2.02 billion, significantly below an earlier estimate of US $2.94 billion.

Since completion, the “Wu-Yang Viaduct” has been highly praised for its immediate impact and success in restoring smooth and fast flowing traffic to this section of National Freeway No 1. Measurable benefits have included shortening the travel time along the section by increasing the peak-hour vehicular speed from 40-90km/h, mitigating an estimates 32,500tonnes of carbon emissions/ year and saving fuel costs of US $1.7 million/ year.

The project is also a testament of how the collective efforts of the government, designers and builders can realise an innovative road engineering design solution, which answers to the needs of society and while helping conserve the environment.

Related Content

  • Hoover Dam’s innovative new bridge bypass
    April 12, 2013
    Soaring over 271m above the Colorado River, the Hoover Dam Bypass overlooks one of America’s greatest icons and assets. The October 2010 opening of the bypass improves the security of the historic Hoover Dam by removing through traffic from US Route 93. This has reduced its vulnerability to a terrorist attack against an international landmark and guarded the most sustainable source of electricity and the scarce water supply for the entire southwestern United States. By diverting traffic from the hairpin tur
  • Italy's new southern highway route
    May 13, 2021
    An important new highway route is currently under construction in South Italy
  • New road links will cut congestion in St Petersburg
    June 20, 2016
    Road building will solve the problem of traffic jams in St Petersburg – Eugene Gerden writes The authorities in Russian city St Petersburg plan to solve the problem of traffic jams in the city during the next few years. The strategy is expected to be achieved through road building and the improvement of transport connections between different districts in the city. Implementation of these plans will take place as part of the decree 355 "Of the Strategy of St Petersburg Economic and Social Development
  • Stockholm’s new bypass
    March 8, 2021
    Tunnels make up 18km of the 21km of the Swedish capital’s E4 Bypass mega-project. It will have taken 15 years from start to opening in 2030, if all goes well