Skanska wins Norway E16 phase three

The winning bid for the 8.4km section from Bjørum to Skaret was €279 million.
By David Arminas November 26, 2020 Read time: 2 mins
Bjørum-to-Skaret (Credit: Statens vegvesen)

Skanska has won a turnkey contract for construction of Norway’s E16 highway from Bjørum to Skaret in the municipality of Hole.

Skanska’s winning bid for the 8.4km section was €279 million and done in co-operation with consulting firm Aas-Jakobsen. It was lower than bids from competitors Implenia/Multiconsult and AF Gruppen/Norconsult.

Work for four-lane motorway to have a speed limit of 100kph will include construction of two motorway junctions, five bridges of up to 220m in length, an 800m-long tunnel and one at 3.4km.

The stretch of 3.5km up to Sollihøgda has a maximum 5% grade and is characterised by large rock cuts to be done with extensive blasting work and earth relocation.

The project is part of Norway’s National Transport Plan 2018-29 and completion is expected in summer 2025.

The existing E16 will be maintained as a local road with additional cycling and walking paths constructed.

The new E16 is part of a larger plan, the E16 Sandvika-to-Skaret-to-Høgkastet. The aim is to develop a faster and more predictable travel time connection between Oslo and Øvre Buskerud, Vest-Oppland and Vestlandet.
    
The overall E16 project is divided into four sections.

The Sandvika-Wøyen section was started in 2015 and opened to traffic in 2019. The local road system around Sandvika (the Sandvika ring) will be completed in the summer of 2021.

The Wøyen-Bjørum section has been completed as a four-lane motorway and was opened in 2009.

The section from Skaret to Høgkastet has been approved and is in the planning stage.

 

Video: Construction of the Bjørum-to-Skaret includes two motorway junctions, five bridges of up to 220m in length, an 800m-long tunnel and one at 3.4km

For more information on companies in this article

Related Content

  • Important road works for Slovakia
    July 6, 2023
    Important road connection works are underway for Slovakia.
  • New UK road link planned
    August 25, 2020
    A new UK road project is being planned.
  • Florida highway rebuild project
    May 2, 2018
    Rebuilding a congested stretch of highway in Florida will cut congestion and boost safety for commuters - Mike Woof writes. Florida’s 214km-long I-4 highway provides a key transport route between Tampa and Daytona Beach, but has an unenviable reputation for both congestion and safety, with frequent delays due to heavy traffic as well as crashes. The stretch running through the city of Orlando is particularly prone to jams at peak periods, with huge traffic volumes resulting in vehicles having to slow to a c
  • Bertha ends her Alaskan Way voyage in Seattle
    December 21, 2017
    Seattle's State Route 99 viaduct is coming down. David Arminas was on site. Bertha, the world’s largest diameter earth pressure balance tunnel boring machine, with a cutterhead diameter of 17.5m, is no more. Her 2.7km journey underneath the waterfront area of Seattle finished on April 4 and the power went off for the last time on an extraordinary TBM that had finally completed an extraordinary job. “A small sidewalk job would have had more impact on city traffic than we have had,” says Brian Russell a v