A rough ride for Denmark’s National Road Directorate

Denmark’s National Audit Office has criticised the Danish National Road Directorate for consistently miscalculating the level of investment required for road projects. The Road Directorate – Vejdirektoratet - used 33% less than budgeted for road projects from 2007-2017. The audit office said that "budget calculations by the transport ministry, including the Road Directorate, have not been accurate enough". Jens Holmboe, head of the Road Directorate, rejected the criticism, saying that the Audit Office
November 1, 2019 Read time: 2 mins
Denmark is not spending enough? (Roskilde Bridge, photo courtesy RBAI joint venture)
Denmark’s 5285 National Audit Office has criticised the Danish National Road Directorate for consistently miscalculating the level of investment required for road projects.


The Road Directorate – Vejdirektoratet - used 33% less than budgeted for road projects from 2007-2017. The audit office said that "budget calculations by the transport ministry, including the Road Directorate, have not been accurate enough".

Jens Holmboe, head of the Road Directorate, rejected the criticism, saying that the Audit Office did not consider the effect the financial crisis had on building projects. The crisis resulted, among other things, in major price decreases for various road projects.

The Vejdirektoratet is responsible for the more than 1,200km of motorways, a number of main roads and many of the country's bridges – a total of about 4,000km. Denmark, being a country mainly of islands, relies on its bridges and tunnels to help unify the nation culturally. It also means that they are vastly more important to the economic well-being of the nation than in most other states.

In  mid-2015, Denmark became the first country in the world to rely on GPS probe data to monitor traffic and congestion on a national scale. It chose INRIX, a provider of transportation intelligence and connected car services, to set up a real-time traffic information system throughout the country. The directorate monitors traffic flow and gridlock across its entire national road network.

Early last year, an Italian joint venture won the construction contract for what will be one of Denmark’s longest bridges, the replacement 4km-long road and rail Storstrom Bridge. The work went to the joint venture of 3481 Condotte and 3869 Grandi Lavori Fincosit along with bridge design consultant Seteco Ingegneria as a subcontractor. Estimated cost is around €550 million for the 24m-wide single-support cable-stayed structure. The European Union will subsidise the work to around €15 million.

World Highways recently interviewed Niels Pedersen, head of bridges at the %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external Danish Road Directorate false https://www.worldhighways.com/categories/road-highway-structures/features/highly-relevant-denmarks-asset-management-for-bridges/ false false%>.

For more information on companies in this article

Related Content

  • Higher rating for new X Crane + tyre from Michelin
    April 18, 2012
    Michelin previewed its new X Crane+ tyre at INTERMAT. The new radial tyre has an ‘F’ speed rating allowing each tyre to carry a payload of 6,700kg at speeds of up to 80km/h. This means the tyre allows cranes between 35 to 1,200tonnes, which often have up to 12 axles each carrying 12tonnes, to run at 80kmh – common in the UK and some other markets. As a precaution Michelin withdrew the previous, lower rated, X Crane design from the UK market as crane owners were running at speeds higher than the tyre’s capac
  • 4x4 Canter is start turn on Mercedes Benz stand
    January 6, 2017
    A 4x4 version of Mitsubishi’s Canter light truck premiered at INTERMAT on the stand of its sister company Mercedes Benz, which distributes the vehicles in Europe. The 6.5tonne GVW vehicle is fitted with a transfer box that diverts half of the torque to the front wheels at the touch of a button and can be engaged while still on the move.
  • 4x4 Canter is start turn on Mercedes Benz stand
    April 19, 2012
    A 4x4 version of Mitsubishi’s Canter light truck premiered at INTERMAT on the stand of its sister company Mercedes Benz, which distributes the vehicles in Europe. The 6.5tonne GVW vehicle is fitted with a transfer box that diverts half of the torque to the front wheels at the touch of a button and can be engaged while still on the move.
  • Dubuis’s cutting-edge crimping
    January 6, 2017
    France-based Dubuis is unveiling its new Neoelec in line BPL36 crimping tool at Intermat 2012.The company, bought by Stanley Black&Decker in 2006, has designed a crimper with 35kN force and 8mm stroke, weighing 2.1kg and capable of 4-185mm² hexagonal crimping.