Poland bidders angry over Astaldi win for Warsaw Ring Road work

Four groups that made bids for building the southern section of the Warsaw Ring Road have filed complaints about how the national road authority GDDKiA chose Astaldi as the winner. Companies appealing to the National Board of Appeal (KIO) are Impresa Pizzarotti, Porr Polska, Salini Polska and IDS-BUD. The offer made by Italian company Astaldi was at least 25% less than the estimated €391 million cost of the project, according to Polish media reports. World Highways reported in February that Astaldi
June 18, 2015 Read time: 2 mins
Four groups that made bids for building the southern section of the Warsaw Ring Road have filed complaints about how the national road authority 1361 GDDKiA chose 1324 Astaldi as the winner.

Companies appealing to the National Board of Appeal (KIO) are Impresa Pizzarotti, 3976 Porr Polska, Salini Polska and IDS-BUD.

The offer made by Italian company Astaldi was at least 25% less than the estimated €391 million cost of the project, according to Polish media reports.

World Highways reported in February that Astaldi’s €290 million bid was the lowest offer for the project. The work calls for a 4.6km section of the route to be constructed, including what will be Poland’s longest road tunnel once complete.

The dispute comes just as an engineering and construction group led by Astaldi signed the largest construction financing package in Turkey’s history – US$5 billion - to refinance existing loans and provide new funding for a $6.4 billion toll road.

Astaldi and its Turkish partners 3338 Nurol Insaat, 3340 Makyol Insaat and Ozaltin Insaat agreed to the loan from nine lenders, including 3321 Deutsche Bank for the 400km road and suspension bridge across the Sea of Marmara. Financial news agency Bloomberg said the loan is the largest for a project in Turkey.

Astaldi said in a written statement that the new financial package will allow completion of the final portion of the 301km route linking the city of Bursa to the Aegean port of İzmir (Phase 2B) and to refinance the sections under construction for the Gebze-Orhangazi-Bursa link (Phase 1 and Phase 2A).

For more information on companies in this article

Related Content

  • Italian firm handling Polish contract
    December 14, 2017
    In Poland a road contract worth some €103.74 million will be carried out by Italian firm Impresa Pizzarotti. The project is for a section of the S61 dual carriageway between Lomza Zachod junction and Kolno junction. The tender process was handled by the Polish road authority, GDDKiA.
  • Deals signed to construct Polish highway project
    August 22, 2017
    Construction of a stretch of the S7 dual carriageway in Poland will commence shortly following the signing of contracts for the work. The stretch, connecting Lotnisko junction with Grojec's ring road, will cost €186.66 million to build. Three contracts were awarded by the Polish General Directorate for National Roads and Motorways (GDDKiA) for the work. Rubau Polska will build a 7km section while a 14.8km stretch will be built by IDS-Bud and Mota-Engil Central Europe will build an 8km portion of the link.
  • Warsaw ring road under construction
    March 3, 2017
    Work is commencing on Warsaw’s ring road project. The work will be carried out on the A section of the Warsaw Southern Ring-Road (POW). This stretch of the ring road runs from Pulawska to the Przyczolkowska junction and is costing just over €278 million to construct, with the project being managed by Italian contractor Astaldi. One of the more complex and challenging aspects of the work will be constructing a tunnel section underneath a metro route.
  • PBDiM and Gulermak start on Warsaw's ring road
    June 26, 2017
    Work has started on the 18.5km southern ring road around the Polish capital Warsaw.