Poland bidders angry over Astaldi win for Warsaw Ring Road work

Four groups that made bids for building the southern section of the Warsaw Ring Road have filed complaints about how the national road authority GDDKiA chose Astaldi as the winner. Companies appealing to the National Board of Appeal (KIO) are Impresa Pizzarotti, Porr Polska, Salini Polska and IDS-BUD. The offer made by Italian company Astaldi was at least 25% less than the estimated €391 million cost of the project, according to Polish media reports. World Highways reported in February that Astaldi
June 18, 2015 Read time: 2 mins
Four groups that made bids for building the southern section of the Warsaw Ring Road have filed complaints about how the national road authority 1361 GDDKiA chose 1324 Astaldi as the winner.

Companies appealing to the National Board of Appeal (KIO) are Impresa Pizzarotti, 3976 Porr Polska, Salini Polska and IDS-BUD.

The offer made by Italian company Astaldi was at least 25% less than the estimated €391 million cost of the project, according to Polish media reports.

World Highways reported in February that Astaldi’s €290 million bid was the lowest offer for the project. The work calls for a 4.6km section of the route to be constructed, including what will be Poland’s longest road tunnel once complete.

The dispute comes just as an engineering and construction group led by Astaldi signed the largest construction financing package in Turkey’s history – US$5 billion - to refinance existing loans and provide new funding for a $6.4 billion toll road.

Astaldi and its Turkish partners 3338 Nurol Insaat, 3340 Makyol Insaat and Ozaltin Insaat agreed to the loan from nine lenders, including 3321 Deutsche Bank for the 400km road and suspension bridge across the Sea of Marmara. Financial news agency Bloomberg said the loan is the largest for a project in Turkey.

Astaldi said in a written statement that the new financial package will allow completion of the final portion of the 301km route linking the city of Bursa to the Aegean port of İzmir (Phase 2B) and to refinance the sections under construction for the Gebze-Orhangazi-Bursa link (Phase 1 and Phase 2A).

For more information on companies in this article

Related Content

  • Bridge formwork solutions complete big bridge picture
    July 2, 2014
    Advanced bridge formwork solutions are allowing contractors to complete vital major highway infrastructure projects covering Norway, Sweden, Estonia and Poland. Guy Woodford reports Building the Labbdalen bridges in Norway is a key feature of the E6 highway improvement programme. Main project contractor HÆHRE tasked RMD Kwikform and Teknikk with supplying a complete formwork and shoring solution that could tackle the challenging Norwegian terrain, whilst preserving the environment. Situated two hours
  • Completion of Prague’s outer ring-road Běchovice section for 2024
    July 24, 2019
    Completion of Prague’s outer ring-road connecting the D1 motorway with Běchovice town to the north should be in 2024, a year earlier than planned. Czech prime minister Andrej Babiš made the announcement, saying the 2025 date set by the Czech Highway Authority was too far off, according to local media. The national Czech News Agency reported that the 12.5km section will cost around €365 million. Transport minister Vladimíra Kremlík said that the state will have to acquire land from up to 500 land ow
  • Armenia north-south highway route
    October 9, 2017
    Plans are being drawn up in Armenia for the new North-South Highway project. Measuring some 556km in all, the project is expected to cost in excess of US$2 billion to construct, although there it is possible that the final pricetag will be somewhat higher. The country's Ministry of Transport says that the southern section of the highway between Artashat and Megri will cost $1.5 billion to build alone.
  • Italy's new southern highway route
    May 13, 2021
    An important new highway route is currently under construction in South Italy