Netherlands projects in hand

Several key projects are in hand in the Netherlands.
By MJ Woof February 4, 2021 Read time: 1 min
New road projects are being carried out in the Netherlands – image courtesy of © Charles Knoblich, Dreamstime.com

The planned Groningen Ring Zuid project now looks likely to cost more than originally estimated. Work started on the project in 2016 and should take until 2024 to complete. Originally the project was expected to cost €435 million but an agreement has been reached over the work that the maximum pricetag could now be allowed to reach €552 million. The work is being carried out by contractor Combinatie Herepoort (CHP), which will pay a portion of the extra cost while the Province of Groningen will provide an additional €78 million.

However, planned widening work for the busy A12 and A15 routes now looks to have been blocked. Questions have been raised over the expected emissions levels resulting from these road projects and the way these have been determined. The work has been blocked by the State Council as a result. Costing €1.4 billion, the A15 highway alignment traverses the Rijntakken nature reserve, giving rise to some environmental pressures.

Related Content

  • Auckland’s causeway project
    April 4, 2014
    When it is finished in early 2017, the causeway on Auckland’s North-western Motorway, State Highway 16, will have been raised 1.5m to stop flooding at extreme high tides. There will be four lanes city-bound and four/five lanes westbound with dedicated bus lanes in each direction, and the existing North-western cycleway that runs alongside it will be upgraded.
  • Highway work boost in North Africa
    August 21, 2012
    North Africa is seeing construction business return - Mike Woof reports After a troubled period, stability looks to be returning to North African nations, which can only be good for the road construction sector. First Tunisia, then Egypt and finally Libya saw tumultuous revolts against the previous autocratic (and in one case at least, despotic) rulers. All three nations are now benefiting from a return to stability, with economic growth also improving once more.
  • Russian road project faces delay
    June 19, 2019
    Russia’s Sochi highway project will not now be completed by 2024. The original plan was to build a 119.km new route to replace the existing A147 route that connects Dzhubga with Sochi. Because of the challenging terrain, this project to build a new four lane highway without the twists and turns of the existing route would have been extremely costly, with a pricetag of as much as US$18 billion. However the project has now been downgraded as being of a lesser priority than other Russian road projects ongoing