More tenders for Lower Thames Crossing

The winners will build 23km of road connecting to the UK’s longest road tunnel.
By David Arminas April 1, 2021 Read time: 3 mins
The €2.23 billion Lower Thames Crossing - the most environmentally sustainable road project in the UK (north entrance)

Highways England has opened tenders to build two linking roads as part of the €2.23 billion (£1.9 billion) Lower Thames Crossing project near London.

For more than 65 years the Dartford Crossing has been the only River Thames crossing between counties Kent and Essex. Highways England – the government agency responsible for England’s major roads and motorways - says that the ageing bridge and tunnel combination is designed for 135,000 vehicles a day. But it now often sees 180,000 a day which creates congestion at peak periods.

The agency says the planned Lower Thames Crossing will improve journeys by almost doubling road capacity across the river.

The two successful bidders will build 23km of road in total that will connect the longest road tunnel in the UK to the country’s strategic road network.

The €705 million (£600 million) Kent Roads two-stage design and build contract is a for the route from the A2/M2 corridor to 1km south of the southern tunnel entrance, including strategic utilities and environmental interfaces. Work includes 6km of road, including a multi-level junction to connect the A2 to the Lower Thames Crossing. Two so-called “Green Bridges” at Thong Lane & Brewers Road, will combine green spaces with walking, cycling and vehicle access and provide better connectivity for the landscape, ecology and habitats. Brewers Road will also cater for horse riders.

The €1.53 billion (£1.3 billion) Roads North of the Thames contract - also a two-stage design and build deal - will deliver the route from 1km north of the northern tunnel entrance to Junction 29 of the M25 motorway. New link roads are required to connect the route with the M25, A13 and A1089. The contract comprises 16km of road to take the route through the A13 and to join the M25 at Junction 29. Five green bridges are combine planned.

The successful bidders and their supply chains will help make the Lower Thames Crossing the most environmentally sustainable road project ever delivered in the UK, according to Highways England. The winners will support delivery of landscaping that will increase the biodiversity value of the area by 15% by planting over 260 hectares of woodland, converting 400 hectares of arable land into semi-natural habitats and creating new ponds, waterways, ditches and hedgerows. Seven green bridges will connect habitats and species either side of the new road.

The two roads contracts are the final of package of three main works packages to be procured for the scheme. Already awarded are the €2.35 billion (£2 billion) Tunnels and Approaches package and the €191 million (£162.5 million) Integration Partner contract awarded to Jacobs earlier in the year.

“Our challenge is to build the new crossing in a way that not only supports the next generation of low carbon vehicles, but minimises our footprint, and allows us to enhance the natural environment and leave a positive legacy for our neighbours and users,” said Matt Palmer, executive director of the Lower Thames Crossing project.

Related Content

  • Cables up for Romania’s Brăila Bridge
    June 16, 2021
    The Astaldi and IHI Infrastructure Systems joint venture reports that work will soon start on the road deck for Romania’s Brăila Bridge.
  • Iterchimica’s Gipave used in major UK road trial
    October 3, 2024
    This is the first time graphene-enhanced Gipave has been applied on the UK’s strategic road network - major highways and motorways - and follows ongoing trials on local roads.
  • The A14 Cambridge to Huntingdon improvement scheme takes shape
    May 31, 2017
    Highways England’s project manager gives sneak peek into progress on the UK’s biggest road upgrade now under construction. Road construction workers often find interesting buried items when building roads and the UK’s A14 Cambridge to Huntingdon improvement scheme is proving the point. It’s been less than half a year since construction started on the €1.76 billion A14 scheme, Highways England’s largest ongoing project. Highways England is the wholly government-owned company responsible for modernising, main
  • Europe closes in on the crossings
    September 27, 2017
    The Mersey Gateway bridge project off England’s west coast passed a milestone recently with the first joining of two of the deck sections. The key segments, as the sections are called, link the north approach viaduct to the north pylon deck span and are the first of four deck-joins scheduled for this summer. In total, there are five sections of bridge deck and approach roads that need to be joined.