Kenya port suspension bridge project makes progress

A new suspension bridge in Kenya’s key port city, Mombasa, will help unlock potential – Shem Oirere reports Plans for the construction of a US$200 million suspension bridge in Kenya heva moved a notch higher. The country's urban roads agency recently announced the shortlisting of three bidders for the design, finance, construct, operate, maintain and transfer public private partnership (PPP) contract model. Kenya Urban Roads Authority (KURA) is a state agency that manages, develops, rehabilitates and mai
January 15, 2019 Read time: 4 mins
Mombasa’s busy port will benefit from the new suspension bridge connection
A new suspension bridge in Kenya’s key port city, Mombasa, will help unlock potential – Shem Oirere reports


Plans for the construction of a US$200 million suspension bridge in Kenya heva moved a notch higher. The country's urban roads agency recently announced the shortlisting of three bidders for the design, finance, construct, operate, maintain and transfer public private partnership (PPP) contract model. 6679 Kenya Urban Roads Authority (KURA) is a state agency that manages, develops, rehabilitates and maintains national urban trunk roads. And Kura announced in late October the shortlisting of Nyali Connect Consortium, IHI-Join-Acciona Consortium and Strabag AG for the 2nd Nyali Bridge Public Private Partnership project in the country's second biggest city of Mombasa.

Nyali Connect Consortium includes Vinci Highways, Meridiam and Vinci Concessions while IHI-Join-Acciona is a consortium of Japan Overseas Infrastructure Investment Corporation for Transport and Urban Development and Acciona. Other bidders that had responded to KURA's Request for Qualification were China Communication Construction Company and a consortium of Mota Engil Africa, AIIM, Egis and Orascom.

“It is the qualified firm that the government will get into a deal with. We want to start negotiations and see who can offer the best deal from the three,” KURA Communications Officer John Cheboi told Business Daily in early October.

KURA's Manager for Transport Economics Richard Kyalo said previously that the interest by five reputable international infrastructure firms in developing the bridge “is a sign of strong interest by the market on the project and a mark of confidence in the procurement process.”

The option of the PPP model for constructing the bridge is a strategy by Kenya to mobilise private capital and leverage private sector efficiencies and innovation in delivery of key infrastructure projects outlined in the country's economic blueprint, Vision 2030.

The 2nd Nyali Bridge project is one of those listed under Kenya's PPP Programme and are at various stages of development. By June 2018, there were 72 PPP projects in the pipeline, 67 of which were approved under the solicited process and five approved as Privately Initiated Investment Proposals, according to Kenya's National Treasury.

The preferred bidder will construct a 600m suspension bridge over the Tudor creek to connect Mombasa Island to Mombasa Northern mainland through the Nyali region. The bridge will be tolled with a six-lane dual carriageway having three lanes on either side.

The bridge, which is to be constructed 500m to the south of the existing Nyali bridge, will have steel carriageway beams supported through hangers from two main cables.

KURA says in a project brief that was prepared by Transaction Advisors Deloitte East Africa & India, Iseme Kamau & Maema Advocates, Cliffe Dekker Hofmeyer, HP Gauff Ingenieeure and Earth Care Services with financing from the World Bank, the contractor will, after raising financing, produce the designs, constructed and managed the bridge,  “get compensation from end user charges collected by the government on its behalf.”

The location of the suspension bridge, which is set to be second longest in Africa, was largely picked because the route “has the highest vehicular traffic and therefore must be critical in unlocking perennial traffic gridlocks in and around Mombasa city.”

Associated with the bridge project is the construction of 1.7km of new roads and expansion of 5km of existing roads.

The existing Nyali Bridge, which was built by the Japanese in 1979 is characterised by heavy traffic congestion, with nearly 46,000 daily vehicle trips, a large share originating from Mombasa central business district (CBD). The speed on the route has been reduced to 6km/h especially during morning and evening rush hour, with KURA indicating the bridge is nearing its design capacity of 50,000 vehicle trips/day at a time when the population of Mombasa has more than doubled in the last 39 years to 800,000 from 341,000 in 1979.

“A new bridge to the south of the existing Nyali Bridge would yield the greatest traffic benefits, in terms of traffic operations and capacity, attracted volumes, travel time savings and network connectivity,” according to the project brief.

The County Government of Mombasa has previously said the new bridge can form a large ring road covering Kongowea and the Island’s peripheral areas, avoiding major pedestrian traffic hubs, hence reducing the intensity of vehicular congestion.

KURA could not immediately confirm when the successful bidder will be announced although the project is behind schedule according to an earlier implementation plan. The plan envisaged the notice of contract award to be given in November 2017, with signing of the contract agreement in the same month. Financial close for the bridge project was expected in March of 2018.

For more information on companies in this article

Related Content

  • Brazil roads repaired with Wirtgen equipment
    November 6, 2018
    A large milling machine from Wirtgen has been used to help repair busy roads in the vicinity of São Paulo in Brazil. The roads provide important transport connections as they link São Paulo with Santos, Brazil’s largest port. The Anchieta-Imigrantes highway system provides the main link between the metropolitan region of São Paulo and the port of Santos, the busiest port in Latin America. Construction of the Anchieta highway began in 1947, with Imigrantes following at the start of the 1970s. Today the Anch
  • Asphalt plant for Turkish highway project
    June 27, 2018
    An asphalt plant from Ammann is playing a key role in the construction of a new Turkish highway. An important factor in the selection of the plant for the construction of Turkey’s Northern Marmara Motorway was its ability to utilise fibres. A large portion of the motorway, which serves as a bypass of Istanbul, has been completed. Handling a good deal of the remaining work is Nalbantolu naat, a family-owned business founded in 1995. The company has completed a number of high-profile projects, including
  • JCB excavators JS220 and 370 work close to home
    May 14, 2018
    A fleet of JCB excavators is playing a major role in a road construction project only metres from the factory where they were built. Derbyshire-based earthmoving specialist JC Balls is working for a Carillion-Tarmac joint venture on the A50 Growth Corridor Project A. The contract is part of the National Infrastructure Plan and consists of constructing a grade-separated junction on the A50 dual carriageway to the west of the town of Uttoxeter. Project managed by Amey, the scheme is creating three new
  • Spanish firms interested in US$740mn Chile bridge project
    June 5, 2013
    Spanish companies Sacyr, ACS and OHL will take part in three of the consortia that will bid in the US$740 million contract to build the longest suspension bridge in Chile. Works for the 2.5km Chacao Bridge, connecting the island of Chiloe and Chile's coast line, are expected to be awarded during the first quarter of 2014, with construction due to begin in 2015.