Italian highway link completed

A challenging road construction project is being carried out in Italy within a tight timeframe, with assistance from a new Marini asphalt plant. The project is for the Salerno-Reggio Calabria highway and the work has to be completed before the end of 2016. Local contractor Bulfaro is carryiing out the work to complete surfacing work to the Macrolotto 3.2; a 40km section of the highway between Laino Borgo and Campotenese. This section of the route is at an altitude of over 800m but the work was complicated b
January 24, 2017 Read time: 3 mins
A Marini mobile asphalt plant is playing a key role in the construction of a new highway in Calabria in Southern Italy
A challenging road construction project is being carried out in Italy within a tight timeframe, with assistance from a new 273 Marini asphalt plant. The project is for the Salerno-Reggio Calabria highway and the work has to be completed before the end of 2016. Local contractor Bulfaro is carryiing out the work to complete surfacing work to the Macrolotto 3.2; a 40km section of the highway between Laino Borgo and Campotenese. This section of the route is at an altitude of over 800m but the work was complicated by the fact that the road runs through the Pollino National Park situated in the Calabrian Apennines.

The Italian government set the tight time schedule for the work to be completed and Bufaro took on the surfacing work on behalf of CMB Ghella. The contractor realised it would require a highly mobile, versatile and productive plant for the job and opted to utilise the Marini XPRESS 2500 as a result.

The plant comprises separate trailer units for the cold-feeders, the dryer, the filter and the mixing tower with the hot elevator. A key feature is that the plant can be erected without the need of a crane, which was highly important given the location of the working area for this project. The mixing level is raised up by hydraulic jacks while the screen, transported at the back of the trailer to ensure the unit remains within transport restrictions, is winched on tracks into position above the aggregate hopper.

For this job the machine was specified with five cold feeders, two bitumen hot-oil tanks, one 30m3 self-erecting silo and one 25m3 mobile asphalt storage bin. The plant can deliver a maximum production level of 200tonnes/hour, with an average production over 160tonnes/hour. A high percentage amount of RAP can also be used through the recycling feed into the dryer drum and the mixer.

For this job the plant has already delivered 110,000tonnes of asphalt, comprising both binder and base. This was laid over two and a half months, with up to 10% RAP in the mixer and 20% in the dryer. Once the project is complete the contractor will have produced close to 200,000tonnes of asphalt, including base, binder and wear course and the project is well on track to completion.

For more information on companies in this article

Related Content

  • Finnish airport paving contract
    October 12, 2012
    The Finnish contractor Lemminkäinen is currently working on a paving contract for Finavia, the company which maintains Finland's airports. The contract includes paving milling, as well as paving work for runway 3 and taxiways at Helsinki- Vantaa airport. Lemminkäinen began its operations on the €20 million paving contract in April 2012 and the work is expected to end in the autumn of 2014. Helsinki-Vantaa Airport is an important traffic hub for Finland, as well as for the region, with around 15 million pass
  • Rapid International supplies Collier Group with a batching plant
    December 7, 2017
    Rapid International has supplied Collier Group, based in Fife, Scotland, with the contractor’s first bespoke static concrete batching plant. Rapid, based in County Armagh, Northern Ireland, said that the batching plant was installed at Collier’s Goathill Quarry in Fife. Collier Group’s plant is built on a slope and includes five 4m-wide 80tonne capacity aggregate bins as well as three 160tonne capacity silos. The silos are accessed from the upper ground level, along with filler hoses to fill the four 2500
  • Benninghoven’s modern masterpiece
    April 4, 2013
    In 2012 Benninghoven were commissioned by Kostmann, an Austria-based consortium of companies involved in the production and refinement of raw materials, to build an asphalt mixing plant that included a stone tower silo system. The plant - TBA-3000-U –was to be sited at Weitendorf, a location offering good access to the motorway, the Styria regional capital, Graz, and the Austria-Slovenia border. However, the close proximity of agricultural land and private residential areas called for an adherence to strict
  • Sophisticated concrete plants coming to market
    July 28, 2015
    Concrete production technology is advancing as new systems come to market – Mike Woof reports The efficient production of high-quality concrete is crucial to many construction projects. Whether high-output plants are being used for large bridge or tunnel projects, or smaller mobile units are being used to supply specific operations such as central reservation barrier installation, the quality of the product is vital. Production technology has improved across the board due to the introduction of new systems.