Runway road rehabilitation

The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany.
February 29, 2012 Read time: 3 mins
The BOMAG milling machines worked reliably within a tight time frame
The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany. Upgrade work to the B50 Bundestrasse that connects with the airport is of prime importance and contractor Beitz-Fräsdienstleistungen is widening a 7.5km section of the road. The work will see the road widened and upgraded from two lanes to four-lane and this has been speeded by the high productivity of 172 Bomag planing equipment.

The work was carried out in three different stages with the first stage being planing to a depth of 40mm over a length of 7.5km, an area of 50,000m2. This work removed around 4,500tonnes of material and 180 truck loads were required to haul the milled cuttings away. The second stage was the milling of another 4,500m2 of surface to improve weak points in the road structure, which removed 1,350tonnes of binder and base layers and required a further 55 truck loads to haul the material away. The third and final stage of the milling job was to remove a 150m stretch of 6m wide binder and base layers to a depth of 320mm in front of bridges and this required the removal of 700tonnes of material in a further 28 trucks. In all the milling work required some 6,550tonnes of material to be removed.

The work had to be finished within a tight time frame and the BOMAG BM 2000/60 cold planers worked reliably and productively within the schedule. The planing work had to be completed within a single week during the day from 06.30-17.00 and with a public holiday on the Thursday, the time frame was tighter still. In spite of the surface layer being hard and only a few years old, an average milling speed of 25 m/min was achieved over the 7.5km during the first stage of the planing work. This gave a perfect, clean planed surface that allowed for quick, precise re-laying of the new surface and reduced the time needed for sweeping the road afterwards. During all three stages the average fuel consumption was an encouraging 60-65litres/hour, while cutter wear was minimised due to the effective water spraying system for the planer. Productivity was further boosted by the automatic settings that returned the cutting depth to the same height when each truck carrying the milled material was moved into place under the discharge conveyor.

For more information on companies in this article

Related Content

  • Vögele sets paving record in German capital
    September 16, 2015
    Material transfer vehicles and remixing systems are crucial to delivering quality paving. Using material transfer vehicles (MTVs) can play a major role in delivering high quality road surfaces. These units can help boost quality by minimising the risk of material or thermal segregation. A major road paving project has been carried out in Germany using innovative paving methods. For the first time ever, binder and surface courses were paved over a width of 15.5m. This paving job was carried out on a 4.2km st
  • FAE tops up its top-of-the-range MTH multitask attachments
    November 29, 2019
    FAE Group has restyled its MTH top-of-the-range multitask attachments for 225-375kW (300-500hp) tractors. The MTH is also now available in a high power models, the MTH/HP.
  • Cleaner milling with BOMAG’s new Ion Dustshield system
    April 26, 2018
    BOMAG claims that its new Ion Dustshield system can help reduce dust emissions from milling operations. According to Jonathan Stringham, vice president of marketing at BOMAG: “If you look at the milling process, it’s another emitter of fine dust.” He said that existing dust control systems remove dust from the working area around the operator, but then blow the fumes and dust forward of the machine away from the crew.
  • Advanced, low emission, fuel efficient earthmoving
    February 23, 2012
    Manufacturers are rolling out sophisticated machines for the European, North American and Japanese markets - Mike Woof reports. This year has been a pivotal period for the development of advanced, low emission earthmoving machines. During 2011 an array of manufacturers have introduced new models designed to comply with the latest Stage IIIB/Tier 4 Interim emissions regulations introduced for