The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany.
February 29, 2012 Read time: 3 mins
The BOMAG milling machines worked reliably within a tight time frame
The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany. Upgrade work to the B50 Bundestrasse that connects with the airport is of prime importance and contractor Beitz-Fräsdienstleistungen is widening a 7.5km section of the road. The work will see the road widened and upgraded from two lanes to four-lane and this has been speeded by the high productivity of 172 Bomag planing equipment.

The work was carried out in three different stages with the first stage being planing to a depth of 40mm over a length of 7.5km, an area of 50,000m2. This work removed around 4,500tonnes of material and 180 truck loads were required to haul the milled cuttings away. The second stage was the milling of another 4,500m2 of surface to improve weak points in the road structure, which removed 1,350tonnes of binder and base layers and required a further 55 truck loads to haul the material away. The third and final stage of the milling job was to remove a 150m stretch of 6m wide binder and base layers to a depth of 320mm in front of bridges and this required the removal of 700tonnes of material in a further 28 trucks. In all the milling work required some 6,550tonnes of material to be removed.

The work had to be finished within a tight time frame and the BOMAG BM 2000/60 cold planers worked reliably and productively within the schedule. The planing work had to be completed within a single week during the day from 06.30-17.00 and with a public holiday on the Thursday, the time frame was tighter still. In spite of the surface layer being hard and only a few years old, an average milling speed of 25 m/min was achieved over the 7.5km during the first stage of the planing work. This gave a perfect, clean planed surface that allowed for quick, precise re-laying of the new surface and reduced the time needed for sweeping the road afterwards. During all three stages the average fuel consumption was an encouraging 60-65litres/hour, while cutter wear was minimised due to the effective water spraying system for the planer. Productivity was further boosted by the automatic settings that returned the cutting depth to the same height when each truck carrying the milled material was moved into place under the discharge conveyor.

For more information on companies in this article

Related Content

  • Asphalt paving advances being developed
    April 20, 2018
    Sumitomo is offering a series of special pavers, in addition to its conventional units. The modified machines are aimed at a range of specific applications and are based on the standard models. The HTP60W is a tack coat paver based on the standard HA60W model. The machine has the firm’s J- Screed with electric heating as standard and allowing hydraulic extension from 2.3-6m, while compaction is by tamper and vibration. The spraybars allow tack coats to be applied to the full paving width.
  • Reducing plant noise
    February 7, 2012
    German quarrying firm Oetelshofen Kalk has cut noise emissions by half and tripled machine service life, by installing dual hardness rubber liners in its crushing plant. Based in Wuppertal, the Oetelshofen quarry company produces 2 million tonnes of limestone products/year, and has a turnover of €35 million/year.
  • Gully and road waste is still overlooked and needlessly sent to landfill
    February 16, 2015
    Road sweepings and gully waste could be recycled, diverting it away from landfill reports *Peter Craven. Highway authorities across Europe have been stockpiling millions of tonnes of rock salt and grit which is destined to be spread onto the road network during the winter months in order to keep them clear. But according to Craven, road sweepings and general gully waste provide a ready source of these materials, as well as delivering significant environmental and financial savings. Road sweepings and gully
  • Simex levers big green gains
    July 7, 2023
    Innovative asphalt recycling and road maintenance solutions from Simex draw on the levers of savings, innovation and environmental sustainability.