Runway road rehabilitation

The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany.
February 29, 2012 Read time: 3 mins
The BOMAG milling machines worked reliably within a tight time frame
The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany. Upgrade work to the B50 Bundestrasse that connects with the airport is of prime importance and contractor Beitz-Fräsdienstleistungen is widening a 7.5km section of the road. The work will see the road widened and upgraded from two lanes to four-lane and this has been speeded by the high productivity of 172 Bomag planing equipment.

The work was carried out in three different stages with the first stage being planing to a depth of 40mm over a length of 7.5km, an area of 50,000m2. This work removed around 4,500tonnes of material and 180 truck loads were required to haul the milled cuttings away. The second stage was the milling of another 4,500m2 of surface to improve weak points in the road structure, which removed 1,350tonnes of binder and base layers and required a further 55 truck loads to haul the material away. The third and final stage of the milling job was to remove a 150m stretch of 6m wide binder and base layers to a depth of 320mm in front of bridges and this required the removal of 700tonnes of material in a further 28 trucks. In all the milling work required some 6,550tonnes of material to be removed.

The work had to be finished within a tight time frame and the BOMAG BM 2000/60 cold planers worked reliably and productively within the schedule. The planing work had to be completed within a single week during the day from 06.30-17.00 and with a public holiday on the Thursday, the time frame was tighter still. In spite of the surface layer being hard and only a few years old, an average milling speed of 25 m/min was achieved over the 7.5km during the first stage of the planing work. This gave a perfect, clean planed surface that allowed for quick, precise re-laying of the new surface and reduced the time needed for sweeping the road afterwards. During all three stages the average fuel consumption was an encouraging 60-65litres/hour, while cutter wear was minimised due to the effective water spraying system for the planer. Productivity was further boosted by the automatic settings that returned the cutting depth to the same height when each truck carrying the milled material was moved into place under the discharge conveyor.

For more information on companies in this article

Related Content

  • Scotland’s new Queensferry Crossing over the Forth Estuary
    December 23, 2015
    The new Queensferry Crossing under construction in Scotland will be the third landmark bridge spanning the Forth Estuary - Mike Woof writes When the new Queensferry Crossing over the Forth Estuary opens at the end of 2016, it will be the third landmark bridge to be built spanning this short stretch of water. Lying alongside the existing road bridge and the historic rail bridge, this new structure will be as groundbreaking as the two earlier crossings were at the time of their construction.
  • Scottish mountain highway toast to SuDS
    June 24, 2013
    Highway degradation and surface water pollution in an environmentally sensitive area of the Scottish Cairngorms Mountains, famous for its whisky production, are said to have been tackled with an innovative SuDS Solution from Hydro International. Poor drainage, flooding and freezing weather had led to a landslip and extreme surface degradation along a section of the narrow A95 that descends on a 10% gradient with tight bends to the beautiful village of Craigellachie on the River Spey, near Elgin. Situated im
  • Asphalt plant producers see major worldwide successes
    November 21, 2014
    Asphalt plant manufacturers report major supply deals for highway and construction projects - Pat Smith writes International asphalt plant manufacturers have been reporting major successes with their products, which are now working on highway and airport projects worldwide.
  • Cleaner milling with BOMAG’s new Ion Dustshield system
    June 12, 2018
    BOMAG claims that its new Ion Dustshield system can help reduce dust emissions from milling operations. Jonathan Stringham is vice president of marketing at BOMAG and said, “If you look at the milling process, it’s another emitter of fine dust.” He said that while existing dust control systems remove dust from the working area around the operator, many then exhaust the dust forward of the machine away from the crew. However this new package is said to clean up the working area around the milling machine, s