The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany.
February 29, 2012 Read time: 3 mins
The BOMAG milling machines worked reliably within a tight time frame
The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany. Upgrade work to the B50 Bundestrasse that connects with the airport is of prime importance and contractor Beitz-Fräsdienstleistungen is widening a 7.5km section of the road. The work will see the road widened and upgraded from two lanes to four-lane and this has been speeded by the high productivity of 172 Bomag planing equipment.

The work was carried out in three different stages with the first stage being planing to a depth of 40mm over a length of 7.5km, an area of 50,000m2. This work removed around 4,500tonnes of material and 180 truck loads were required to haul the milled cuttings away. The second stage was the milling of another 4,500m2 of surface to improve weak points in the road structure, which removed 1,350tonnes of binder and base layers and required a further 55 truck loads to haul the material away. The third and final stage of the milling job was to remove a 150m stretch of 6m wide binder and base layers to a depth of 320mm in front of bridges and this required the removal of 700tonnes of material in a further 28 trucks. In all the milling work required some 6,550tonnes of material to be removed.

The work had to be finished within a tight time frame and the BOMAG BM 2000/60 cold planers worked reliably and productively within the schedule. The planing work had to be completed within a single week during the day from 06.30-17.00 and with a public holiday on the Thursday, the time frame was tighter still. In spite of the surface layer being hard and only a few years old, an average milling speed of 25 m/min was achieved over the 7.5km during the first stage of the planing work. This gave a perfect, clean planed surface that allowed for quick, precise re-laying of the new surface and reduced the time needed for sweeping the road afterwards. During all three stages the average fuel consumption was an encouraging 60-65litres/hour, while cutter wear was minimised due to the effective water spraying system for the planer. Productivity was further boosted by the automatic settings that returned the cutting depth to the same height when each truck carrying the milled material was moved into place under the discharge conveyor.

For more information on companies in this article

Related Content

  • Out of sight
    July 16, 2012
    With traffic volumes increasing around the world, many existing road links will need to be upgraded or replaced in coming years The need for new road tunnels is particularly intense in many dense urban areas, due to environmental requirements that mean new road links will have to be installed underground. However, improving existing road tunnel links is providing a very large part of the business for this specialised construction segment at present.
  • VIDEO: Bridge demolition on key A90 route in Scotland
    November 4, 2015
    Demolition work has been carried out on a bridge crossing the busy A90 route in Scotland, just to the north of the capital, Edinburgh. The bridge carried the B900 over the A90 but had to be removed as its narrow design prevented the route from being upgraded to full motorway status. The first stage of the demolition work was carried out on October 24th and 25th, with the second stage on October 31st and November 1st and final remedial work to be carried out on November 14th and 15th.
  • Special mixes produced for a race track in Indonesia
    March 4, 2022
    International motorcycle racing has returned to Indonesia with help from asphalt plants supplied by Lintec & Linnhoff after a 24-year hiatus
  • Mixing recycled and fresh asphalt reduces costs
    February 14, 2012
    An innovative asphalt plant is allowing the use of recycled materials and achieving major cost benefits - Mike Woof reports. UK construction firm FM Conway is seeing the benefit of the €11.5 million (£10 million) it has invested in its asphalt production facilities at Erith in Kent, close to UK capital London, since buying the site in 2005. The biggest single investment in the facility has been a new Benninghoven asphalt plant, which was commissioned in June 2010 and is now the core of the Erith operation.