Texas highway project tackles congestion

A new highway project in Texas will tackle peak congestion
February 20, 2012 Read time: 4 mins

A new highway project in Texas will tackle peak congestion

A major highway job is underway in Texas at present where contractor Northgate Constructors, a joint venture between Kiewit & Zachary, is working on the huge DFW Connector Project. Northgate is using equipment from Guntert & Zimmerman, an S850, S600, and two TC1500s, on the job.

The DFW Connector Project is a heavily commuted area in North Texas, with more than 250,000 vehicles/day using the corridor. To reduce traffic congestion where two of the areas most heavily travelled highways meet and to ease access into the Dallas/Fort Worth Airport, the Texas Transportation Commission authorised a request for Comprehensive Development Agreement (CDA) proposals in March 2006 for the reconstruction of State Highways 114 and 121 north of the DFW Airport.

In March 2009, the project was conditionally awarded to NorthGate Constructors (NorthGate); a Kiewit Texas Construction led joint venture with Zachry Construction Corporation. The combination of Kiewit's design-build experience and Zachry's strong position in Texas made NorthGate an effective partnership for the DFW Connector project.

The US$1.02 billion project is publicly funded, with $667 million from public fuel taxes, $250 million from 1088 American Recovery and Reinvestment Act funds, and $107 million from bond proceeds for right-of-way acquisition. The initial phase is for 13.5km, with the entire project stretching 23.2km through Grapevine, Southlake and Irving and doubling road capacity in some areas. When completed, the DFW Connector will include a combination of new mainlanes, toll managed lanes, and continuous frontage roads. At its widest point, the highway will feature 24 lanes between International Parkway and Main Street, while the work also includes rebuilding existing bridges, improving drainage and a sophisticated new transportation system. With some 420,000m3 of CRCP being placed and the construction of 42 new bridges, the project is a substantial one.

The DFW connector features a continuously reinforced pavement design. The pavement section consists of 305-915mm of lime treated sub-grade, 305mm of recycled aggregate base depending on the location within the project with 63.5mm of asphalt bond breaker. The pavement design is a continuous reinforced concrete pavement with 330mm thicknesses for the managed lanes, mainlanes and ramps and 254mm thicknesses for the frontage roads and side streets. Many of the roads and side streets will be paved in widths varying from 3.66-3.73m to include the shoulder and monolithic curb using the S600 paver.

Several of the paving pulls and widths were selected to allow traffic movements throughout the project. Because of the various traffic configuration changes and equipment moves, NorthGate needed equipment that would be easy to transport and change widths, with the contractor selecting Guntert & Zimmerman S600 and S850 pavers for the work. The S600 features the patented VariWidth frame width change system, which allows the double telescopic tractor frame to change width quickly, using rollers and an optional hydraulic clamping puck system. The S600 tractor allows the contractor to quickly switch between applications and paving widths and its narrow profile is said to be useful for the DFW Connector's tight pouring conditions. In standard paving mode, there is less than 610mm from the edge of the pavement to the widest point on the paver with sensor support arms removed. The S600 was supplied with Guntert & Zimmerman's new ZeroKit, which allows contractors to pave zero clearance applications. The A-Frame support means that the standard paving kit can be used with or without TeleEnds at either side of the S600 end bolsters. The ZeroKit is designed to pave widths out to 3.6m and does not require any counterweight, while featuring the firm's universal bolting pattern. This allows the S600 to be converted from standard paving configuration to offset configuration in less than four hours. The steel A-Frame prevents deflection and ensures a rigid pan and this is secured to the bolster using 12 standard 25.4mm bolts.

Both the S600 and S850 are equipped with G&Z's patented TeleEnds, telescopic paving kit end Sections, which allow the contractor to change paving kit widths in a couple of hours using a one or two person crew. The TeleEnds give the contractor 914mm of quick width change for each end section, a total of 1.83m if two are used. The S600 and S850 are also equipped with automatic 90° steering, giving the contractor more versatility for moving around the jobsite. The paving kit, front tie bar inserters and many of the other optional attachments on the S600 are interchangeable between the S600 and S850.

For more information on companies in this article

Related Content

  • Wirtgen machines help with road recycling in Italy
    March 18, 2016
    One of the first Wirtgen W 200 Hi cold milling machines off the assembly line is now being used for road recyling work in southern Europe. The versatility of the machine due to its novel 400mm offset drum capability has proven extremely useful for the contractor in Italy. Tuscany–based Endi Asfalti is now using the large and highly productive W 200 Hi for a wide range of milling jobs that would previously have been carried out using a combination of large and small milling machines. The proven W 200 milling
  • New racetrack benefits from new technology
    December 3, 2014
    The use of new technology has helped pave the way for a new US racetrack Saving construction costs and meeting tight tolerances, sophisticated technology has helped deliver a quality racetrack surface within tight time constraints. The National Corvette Museum (NCM) in Bowling Green, Kentucky, lies close to Interstate 65 and now features a brand new racetrack, constructed with the assistance of the latest machine control technologies.
  • Wirtgen SP 1500 dual paver solves four problems at once
    December 8, 2016
    Four job sites, four contractors, four German states, one paving method: Dual-layer concrete paving with the slipform paver SP 1500 from Wirtgen is on the road to success in Germany. Swayed by the numerous economic and technical advantages, more and more planning engineers are opting for this technology when rehabilitating concrete highways.
  • Kilsaran power paves with Vögele
    July 31, 2012
    Kilsaran, a leading Irish contractor, building materials supplier and producer of concrete products, has completed construction of 11,000m² of hard standing at its first dedicated mortar plant using Vögele's most powerful wheeled paver. The plant in Brownstown, County Kildare, will produce a variety of mortars, including bagged products, for distribution throughout Ireland. The Vögele 1803-2 is one of four such machines operated by the company, and it complements a range of plant, including Hamm compaction