Skip to main content

Texas highway project tackles congestion

A new highway project in Texas will tackle peak congestion
February 20, 2012 Read time: 4 mins

A new highway project in Texas will tackle peak congestion

A major highway job is underway in Texas at present where contractor Northgate Constructors, a joint venture between Kiewit & Zachary, is working on the huge DFW Connector Project. Northgate is using equipment from Guntert & Zimmerman, an S850, S600, and two TC1500s, on the job.

The DFW Connector Project is a heavily commuted area in North Texas, with more than 250,000 vehicles/day using the corridor. To reduce traffic congestion where two of the areas most heavily travelled highways meet and to ease access into the Dallas/Fort Worth Airport, the Texas Transportation Commission authorised a request for Comprehensive Development Agreement (CDA) proposals in March 2006 for the reconstruction of State Highways 114 and 121 north of the DFW Airport.

In March 2009, the project was conditionally awarded to NorthGate Constructors (NorthGate); a Kiewit Texas Construction led joint venture with Zachry Construction Corporation. The combination of Kiewit's design-build experience and Zachry's strong position in Texas made NorthGate an effective partnership for the DFW Connector project.

The US$1.02 billion project is publicly funded, with $667 million from public fuel taxes, $250 million from 1088 American Recovery and Reinvestment Act funds, and $107 million from bond proceeds for right-of-way acquisition. The initial phase is for 13.5km, with the entire project stretching 23.2km through Grapevine, Southlake and Irving and doubling road capacity in some areas. When completed, the DFW Connector will include a combination of new mainlanes, toll managed lanes, and continuous frontage roads. At its widest point, the highway will feature 24 lanes between International Parkway and Main Street, while the work also includes rebuilding existing bridges, improving drainage and a sophisticated new transportation system. With some 420,000m3 of CRCP being placed and the construction of 42 new bridges, the project is a substantial one.

The DFW connector features a continuously reinforced pavement design. The pavement section consists of 305-915mm of lime treated sub-grade, 305mm of recycled aggregate base depending on the location within the project with 63.5mm of asphalt bond breaker. The pavement design is a continuous reinforced concrete pavement with 330mm thicknesses for the managed lanes, mainlanes and ramps and 254mm thicknesses for the frontage roads and side streets. Many of the roads and side streets will be paved in widths varying from 3.66-3.73m to include the shoulder and monolithic curb using the S600 paver.

Several of the paving pulls and widths were selected to allow traffic movements throughout the project. Because of the various traffic configuration changes and equipment moves, NorthGate needed equipment that would be easy to transport and change widths, with the contractor selecting Guntert & Zimmerman S600 and S850 pavers for the work. The S600 features the patented VariWidth frame width change system, which allows the double telescopic tractor frame to change width quickly, using rollers and an optional hydraulic clamping puck system. The S600 tractor allows the contractor to quickly switch between applications and paving widths and its narrow profile is said to be useful for the DFW Connector's tight pouring conditions. In standard paving mode, there is less than 610mm from the edge of the pavement to the widest point on the paver with sensor support arms removed. The S600 was supplied with Guntert & Zimmerman's new ZeroKit, which allows contractors to pave zero clearance applications. The A-Frame support means that the standard paving kit can be used with or without TeleEnds at either side of the S600 end bolsters. The ZeroKit is designed to pave widths out to 3.6m and does not require any counterweight, while featuring the firm's universal bolting pattern. This allows the S600 to be converted from standard paving configuration to offset configuration in less than four hours. The steel A-Frame prevents deflection and ensures a rigid pan and this is secured to the bolster using 12 standard 25.4mm bolts.

Both the S600 and S850 are equipped with G&Z's patented TeleEnds, telescopic paving kit end Sections, which allow the contractor to change paving kit widths in a couple of hours using a one or two person crew. The TeleEnds give the contractor 914mm of quick width change for each end section, a total of 1.83m if two are used. The S600 and S850 are also equipped with automatic 90° steering, giving the contractor more versatility for moving around the jobsite. The paving kit, front tie bar inserters and many of the other optional attachments on the S600 are interchangeable between the S600 and S850.

For more information on companies in this article

Related Content

  • Brisbane's highway of distinction
    August 2, 2012
    A massive AU$2 billion update of the Gateway Motorway in Queensland is underway to improve an infrastructure stretched by population boom. Report and photographs by Adrian Greeman Just 20 years after the Australian city of Brisbane built its Gateway Motorway with a high slim signature bridge dominating the river skyline, the road is being completely revamped. Some 12km of urban route on the south of the Brisbane River is being expanded to take much increased traffic levels; the north is getting a completely
  • Gardner gets to grips on Miami F1 track
    May 11, 2022
    Gardner Asphalt says that its NTQS1 Trackless Tack is the most innovative non-ionic chemical asphalt emulsion for application where a tenacious tack coat is required.
  • The power of water
    July 18, 2012
    The popularity of hydrodemolition is growing worldwide and was the specified solution for work on two vital Swedish links The hydrodemolition technique, which uses high pressure water jets to remove damaged concrete from various structures, is playing a crucial role in the major restoration of the vital Central Bridge and Söderled Tunnel in the centre of Sweden's capital Stockholm. The 1,550m dual two-lane rectangular box Söderled Tunnel and connecting dual two and three-lane Central Bridge are a vital 2.6k
  • Electric paving becoming a reality
    July 21, 2025
    Electric asphalt paving machines are becoming a reality – Mike Woof writes