Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • Tunnels and bridges, improving Argentina's major road link
    May 2, 2012
    A road improvement plus tunnel and bridge building contract in an area once inhabited by dinosaurs in northern Argentina, is a small but key part of an ambitious project to complete a road that will eventually link the Atlantic and Pacific coasts of Latin America - Adriana Potts reports. Remote, rough and spectacular are words that come to mind when describing the mountains of Ischigualasto in Argentina's northern province of San Juan This is the only place in the world where an undisturbed sequence of rock
  • New UK dual carriageway opening
    December 20, 2016
    Drivers in the UK are to benefit from the opening of a new dual carriageway connection. The section of road is a key route for Highways England, improving the connection between junction 19 of the M6 and junction 7 of the M56 motorways. The new A556 Knutsford to Bowdon link road will cut congestion and journey times for drivers in the area. As part of the £192 million project to build the new dual carriageway between, Highways England has remodelled slip roads at Yarwood Heath and Bowdon roundabouts. The
  • UK to get tough on road works disruption
    March 19, 2012
    Utility companies who take too long to complete their road works in the UK will face higher charges, transport minister Norman Baker has announced. All utility companies who dig up the road must agree a time frame for their works with the local council.
  • Volvo CE’s electric quarry operation commences trials
    August 29, 2018
    Volvo CE is commencing operations of its low emission quarrying operation in Sweden. The facility has a strong focus on electric machines, with diesel-electric hybrid equipment also being used. According to the firm, this is a world first for a quarry facility that can be run almost 'emission-free'. Volvo CE and its customer Skanska have now commenced testing the viability of the Electric Site concept at Skanska’s Vikan Kross quarry, located near Gothenburg in Sweden. The production system at the site