Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • WJ achieves Costain’s Standard of Excellence on smart motorways
    December 14, 2017
    UK road marking specialist WJ has maintained its excellence in supply chain performance for Costain, one of the country’s major highways engineering specialist contractors. Costain Cares is the contractor’s programme to build a long-term sustainable business that creates economic, environmental and social value and their supply chain relationships are fundamental to achieving that vision.
  • Austrian project focuses on paving quality
    April 1, 2014
    Work to improve a section of the busy A12 Inntal highway in Austrian Tyrol, Austria, has been carried out by contractor Strabag. The A12 is one of Austria’s busiest highways and carries heavy traffic volumes, particularly in summer when it is an important holiday route through to Southern Europe. The heavy traffic volumes mean that the road has to withstand high stresses. The Brixlegg branch of Strabag carried out a surface renovation contract on the 5.5km stretch between Kundl and Radfield and focussed on
  • Volvo CE ‘routes’ for Chicago highway project
    May 22, 2014
    More than 2.5 million m³ of material is being moved with a fleet of Volvo Construction Equipment (Volvo CE) articulated haulers in the US state of Illinois. Home to the world’s first skyscraper, the Chicago Bears – and the Blues Brothers – Illinois is the fifth most populous American state and a major transport hub. Industrial cities and agricultural productivity is growing in central and northern Illinois – while natural resources like coal, timber and oil and gas in the south help provide the state with
  • Volvo CE upgrades key asphalt paver models
    December 13, 2018
    Volvo CE is upgrading its key asphalt paver models with the addition of its latest generation technology. The company is now fitting the sophisticated EPMIII electronic pavement management system to its new generation P6820D. This machine is also equipped with the new PaveAssist package, which allows real-time monitoring of machine parameters. The P6820D replaces the earlier C series machine, with power from the latest generation Volvo D6 engine rated at 140KW, and which meets the Stage IV/Tier 4 Final em