Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • Road tolling is vital for good roads
    January 2, 2024
    Upcoming transportation projects are outlined in planning documents throughout America by Mary Scott Nabers
  • Highways England opts for warm mix asphalt
    August 26, 2021
    The company in charge of maintaining England’s strategic highways, including motorways and main roads, is officially shifting its preference towards using warm mix asphalt. Highways England lays out the case for its decision.*
  • A new asphalt plant in Cameroon
    January 27, 2023
    A Lintec CSM4000 containerised asphalt plant in Cameroon has helped with the construction of the country’s first-ever expressway linking its two largest cities, Douala and Yaoundé. The new route replaces an older roadway in use for over three decades that no longer met traffic needs.
  • Work underway on major UK road widening scheme
    January 14, 2013
    Work on a major US$241.9 million (£150m) road widening scheme in the East Midlands region of England has started near Nottingham. The works will focus on an 11.26km (seven mile) stretch of the A453 between M1 Junction 24 and the A52 Nottingham Ring Road – a major link serving Nottingham, the M1 and East Midlands Airport.