Severn Bridge resurfacing complete

Contractor Hanson has completed the latest phase of its resurfacing work on the Severn bridges following the removal of the toll booths and barriers. The contract for Highways England started in December 2018, when the tolls were abolished on the M4 Prince of Wales Bridge and M48 Severn Bridge, and resurfacing was needed for the new road layout. The move to provide free access for drivers from England into Wales is aimed at boosting the Welsh economy. Over the last few weeks Hanson has laid more than
April 30, 2019 Read time: 2 mins
Resurfacing work is complete for the Severn bridges
Contractor 2644 Hanson has completed the latest phase of its resurfacing work on the Severn bridges following the removal of the toll booths and barriers.


The contract for 8100 Highways England started in December 2018, when the tolls were abolished on the M4 Prince of Wales Bridge and M48 Severn Bridge, and resurfacing was needed for the new road layout. The move to provide free access for drivers from England into Wales is aimed at boosting the Welsh economy.

Over the last few weeks Hanson has laid more than 10,000tonnes of base, binder and surface course material to complete the remodelling of the westbound side of the M4 Prince of Wales Bridge. The contracting team laid the final 2,200tonnes overnight in just 12 hours – more than double the amount usually handled on a regular motorway nightshift.

As well as resurfacing the toll booth area, the work has included 950m of the westbound carriageway and a new emergency access road.

Next month (May), the Hanson team will start a similar job on the M48 Severn Bridge; resurfacing the toll booth plaza as well as 1.5km of carriageway on both sides of the bridge.

Hannah Milliner, Severn Bridges General Manager at Highways England said: “This is a significant project for the region and Hanson has worked collaboratively with Highways England and its contractors to ensure that we deliver these works both safely and to schedule. Hanson has played an important part in making toll removal a success. We are currently reaching the final stages of the scheme and drivers will soon be able to benefit from free-flowing motorways.”

For more information on companies in this article

Related Content

  • US land sale completed for US-Canada Gordie Howe Bridge
    June 27, 2017
    Detroit has reached an agreement with the state to sell land, assets and some streets as part of a second bridge between Windsor and Detroit.
  • Highway project in Texas required demolition equipment
    May 1, 2018
    A contractor in Texas has used equipment from Brokk to help out with a tricky highway project. Upgrading work has been carried out on a 6.4km-long stretch of I-35 in San Antonio between Loop 410 NE and Loop 410 S. This stretch of the route was carrying around 185,000 vehicles/day and was suffering increasing levels of congestion at peak periods. Travel times lengthened by 65% during rush hour, while ramps on opposite sides of the interstate caused additional congestion and safety issues. In one section, t
  • Stantec wins upgrade to Florida SR 91
    July 29, 2019
    Canadian contractor Stantec is to lead design work for a 16km upgrade and widening of State Road 91 in the US state of Florida. Work will turn the section of road through Lake County into price-managed lanes for improved travel reliability, according to the company which will be working for Florida’s Turnpike Enterprise, part of the Florida Department of Transportation. Turnpike Enterprise operates a 740km-system of limited access toll highways Stantec’s design for the project, with a construction cos
  • Turkish highways and bridge project financing secured
    June 7, 2018
    The financing package that will pay for Turkey’s €2.43 billion Malkara to Çanakkale highway and 1915 Çanakkale Bridge has now been secured. This follows on from Mott MacDonald completing its technical due diligence of the project documentation. The project will be handled under the PPP model. The centrepiece of the project is the €1.68 billion Çanakkale 1915 bridge. This will be over 4.6km long, with a 2,023m main span that will be the longest in the world for a suspension bridge. It will allow a clearance