Road paving record set

Aggregate Industries has set what it believes to be a road paving record.
By MJ Woof July 10, 2020 Read time: 3 mins
Aggregate Industries was able to complete its paving works on the M23 a full six months ahead of schedule

Aggregate Industries has set what it believes to be a record for asphalt paving in the UK. The firm completed its work early on the M23, to the south of London.

According to the company, collaboration was a key to the successful early completion of the project. The firm was able to lay 52,000tonnes of asphalt on the M23 motorway in just one month. This was achieved using a number of evening and weekend closures and successful collaborative arrangements.

Aggregate Industries says that it was able to engage with external stakeholders across the supply chain to ensure the tight deadlines were met. This enabled the firm to break industry records and complete the work ahead of schedule.

The contract included widening the carriageway to achieve the all lane running requirement, full depth reconstruction of the hard shoulder, central reserve works and collaborative completion of junctions 9,10 and lane four surfacing to enable the road to open for traffic.

With Aggregate Industries’ Contracting Division acting as the lead surfacing partner, the materials for the project were supplied by its Asphalt and Aggregates Divisions, and delivered by its Logistics Team.

The company recycled 100% of the waste material from the pre-existing road using a local facility that crushed and screened it for use in the new asphalt. A proportion of the material will also be used, where possible, in the firm’s larger asphalt plants within its materials. As a result of the close proximity of the recycling facility, less haulage was required reducing the project’s carbon emissions.

Faced with a large tonnage of asphalt to lay in a tight deadline, Tarmac was enlisted as the second surfacing partner. This drew on a long standing relationship with Aggregate Industries through the Highways England Category Management Pavement Framework. The collaboration between all parties; similarities in systems of working; and the ability to share resources, drove efficiencies that resulted in laying 52,000tonnes one month. The pavement works were completed six months ahead of the initial forecasted date.

In addition to the logistical, technical and time requirements for the project, the team also adapted quickly to a new working environment due to the Covid-19 pandemic. The team planned stringent working arrangements to make sure that the project was finished in accordance with social distancing guidelines.  

Paddy Murphy, managing director of Contracting at Aggregate Industries, said: “Not only is this project a great example of collaboration, flexibility and ingenuity within Aggregate Industries, but it is also further testament that even in uncertain times, businesses like ours, and all the parties we worked in close partnership with, are essential to keeping the country moving.”

For more information on companies in this article

Related Content

  • Fast-track Biloxi Bay bridge
    July 18, 2012
    Construction of a bridge destroyed in a hurricane was completed early, and with some added aesthetic benefits Hurricane Katrina, one of the deadliest and costliest natural disasters in US history, made landfall on 29 August, 2005, devastating the Gulf Coast. The US 90 Bridge over Biloxi Bay (connecting the communities of Biloxi and Ocean Springs, Mississippi) was one of many major highway and railroad bridges knocked out of service due to extensive storm damage. The eye of the storm passed 96km west of Bilo
  • How data mining and the intelligence it creates is helping sites run more effectively and efficiently
    December 13, 2022
    In this, the third in our series of top-level roundtable discussions led by World Highways, editor Mike Woof and roundtable host Nadira Tudor talk machine control technology with three world-class experts from Leica Geosystems (part of Hexagon), Topcon, and Trimble. There’s never been a more exciting time to be in construction as innovation makes us more productive, more efficient, more sustainable, and better connected. Autonomy means opportunity.
  • The Path to Climate-Neutral Road Construction
    October 1, 2023
    Machine manufacturers and construction companies around the globe are currently searching for ways to achieve the goal of climate-neutral construction. The challenge here is to successively reduce emissions of CO2 and other harmful gases (summarized to CO2 equivalents: CO2e) around the world to zero over the coming decades. In the road construction sector, this transformation is inextricably linked to the improvement and further development of production and working processes. In the future, machines and construction materials will also be assessed based on the climate-harmful emissions arising from their production and use. However, the focus should not be on individual machines, but on the entire process leading up to the finished product – a road. Ultimately, the decisive factor is the emissions generated per kilometer of newly built or rehabilitated road – the “CO2e per work done”.
  • Webuild proposes Baltimore Bridge design
    May 6, 2024
    VIDEO: The project in the US state of Maryland to replace the collapsed Francis Scott Key Bridge was made free of charge ahead of tomorrow’s state-led virtual industry forum for reconstruction of the bridge.