Tensar’s Glasstex makes the grade in UK’s Smart Motorway upgrade

A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.
February 27, 2017 Read time: 3 mins
Smart move: Foster Contracting is laying 300,000m2 of Tensar’s Glasstex P100 composite on the M3

A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.

More than 130,000 vehicles use the M3 between Junctions 2 (Thorpe and the M25 motorway) and 4a (Farnborough) every day.

As part of 8100 Highways England’s Smart Motorways programme, the capacity of this congested three-lane section is being increased, with hard shoulders converted to ‘smart’ running lanes.

Construction began on site in January 2015. Asphalt surfacing contractor 2399 Tarmac, working for the principal contractor 1146 Balfour Beatty, is carrying out structural resurfacing of the carriageway as part of the project.

“The road is in poor condition, the result of reflective cracking of the asphalt, due to movement of the underlying layers that are made up of both lean mix concrete and bituminous road base,” says Tarmac project manager Barrie Farquhar. “Repairs were needed to strengthen the road and to prevent further cracking, which could have led to water ingress and further deterioration of the concrete.”

Highways England needed a pavement solution that would reduce initial costs, increase service life, as well as minimise maintenance and future disruption.

Consultant 1397 Aecom had specified asphalt reinforcement in the pavement design. Tarmac, subcontractor Foster Contracting and 340 Tensar International proposed Tensar’s Stress Absorbing Membrane Interlayer (SAMI) Glasstex solution, while supporting the required departure from the standard process.

“The SAMI adds tensile stiffness, increasing pavement strength at low strain and mitigating reflective cracking from both traffic-induced stress and from defects in the underlying pavement structure. It also acts as a moisture barrier,” explains Tensar Highways manager Craig Andrews. “This low-maintenance solution will extend the operating life of the pavement, reducing whole-life costs.”

A total of 300,000m2 of Tensar’s Glasstex P100 composite is being laid by Foster Contracting, on both the northbound and southbound carriageways, along the 26km stretch of road – a total of 52km. This composite of glass yarn grid and paving fabric forms an interlayer between the fractured substrate and the asphalt overlay.

“Glasstex adheres to the underlying pavement structure using a straight run bitumen (160/220 pen) bond coat, with a calibrated spray rate of 1.1kg/m², to activate both stress relief and interlayer barrier functions [as given by BS EN 15381: 2008], with reinforcement provided by the grid,” Andrews says.

“Combined with Tarmac’s Ultilayer polymer-modified binder course, this delivers maximum possible crack resistance and durability.”

An added benefit of installing a SAMI Glasstex solution on motorway projects is speed, Andrews adds. “Work typically has to be carried out at night, which obviously limits the amount of time available. Using Glasstex means the reconstruction depth is far shallower. On the M3 it is just 120-150mm, rather than a minimum 360mm with a standard approach, which obviously saves time and, as a result, construction costs.”

With surfacing work progressing well and half the new gantries installed by the summer, the M3 Smart Motorway project looks to be on target to finish as planned in June 2017.

For more information on companies in this article

Related Content

  • ASTM approves fatigue testing standard D8458
    February 17, 2023
    ASTM International says that the new test method, the Three-Point Bending Cylinder (3PBC) Test, can be used to determine the fatigue resistance of asphalt mixtures.
  • Highways England: new agency with long-term investment strategies
    August 18, 2015
    Highways England, created out of the old Highways Agency, was set up on April 1 to oversee a closer relationship between government client and private contractors. World Highways went to a recent forum in London to hear both sides declare their hopes and challenges. Government reforms are often met with a certain amount of scepticism thanks to years of disillusionment over forgotten ministerial promises. Given that, highway contractors in the UK could have been forgiven if they had raised their eyes skyward
  • Kier rebuilds storm-damaged road in England’s tourist Cumbria region
    May 10, 2016
    The first of 20 steel posts have been positioned for major road repairs to the A591 road in northern England under a £40 million project to repair December storm damage. The A591 is a major local authority road in Cumbria. It links the M6 motorway near Brettargh Holt with important Lake District tourist destinations such as Kendal, Windermere, Ambleside, Grasmere and Keswick.
  • Lanes removes 400tonnes of debris from flood-scheme tunnel in UK
    March 28, 2017
    It was “dirty work” for drainage engineers from Lanes Group in the UK when they recently removed 400tonnes of silt and debris from a culvert in northern England. Before sludge removal started, the 3m-wide concrete box culvert under the A38 on the outskirts of the city of Derby had been full almost to its roof. Lanes Group's East Midlands depot, based in Derby, desilted the culvert in a 17-day operation for North Midland Construction, working for Highways England, under its civil engineering framework.