Tensar’s Glasstex makes the grade in UK’s Smart Motorway upgrade

A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.
February 27, 2017 Read time: 3 mins
Smart move: Foster Contracting is laying 300,000m2 of Tensar’s Glasstex P100 composite on the M3

A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.

More than 130,000 vehicles use the M3 between Junctions 2 (Thorpe and the M25 motorway) and 4a (Farnborough) every day.

As part of 8100 Highways England’s Smart Motorways programme, the capacity of this congested three-lane section is being increased, with hard shoulders converted to ‘smart’ running lanes.

Construction began on site in January 2015. Asphalt surfacing contractor 2399 Tarmac, working for the principal contractor 1146 Balfour Beatty, is carrying out structural resurfacing of the carriageway as part of the project.

“The road is in poor condition, the result of reflective cracking of the asphalt, due to movement of the underlying layers that are made up of both lean mix concrete and bituminous road base,” says Tarmac project manager Barrie Farquhar. “Repairs were needed to strengthen the road and to prevent further cracking, which could have led to water ingress and further deterioration of the concrete.”

Highways England needed a pavement solution that would reduce initial costs, increase service life, as well as minimise maintenance and future disruption.

Consultant 1397 Aecom had specified asphalt reinforcement in the pavement design. Tarmac, subcontractor Foster Contracting and 340 Tensar International proposed Tensar’s Stress Absorbing Membrane Interlayer (SAMI) Glasstex solution, while supporting the required departure from the standard process.

“The SAMI adds tensile stiffness, increasing pavement strength at low strain and mitigating reflective cracking from both traffic-induced stress and from defects in the underlying pavement structure. It also acts as a moisture barrier,” explains Tensar Highways manager Craig Andrews. “This low-maintenance solution will extend the operating life of the pavement, reducing whole-life costs.”

A total of 300,000m2 of Tensar’s Glasstex P100 composite is being laid by Foster Contracting, on both the northbound and southbound carriageways, along the 26km stretch of road – a total of 52km. This composite of glass yarn grid and paving fabric forms an interlayer between the fractured substrate and the asphalt overlay.

“Glasstex adheres to the underlying pavement structure using a straight run bitumen (160/220 pen) bond coat, with a calibrated spray rate of 1.1kg/m², to activate both stress relief and interlayer barrier functions [as given by BS EN 15381: 2008], with reinforcement provided by the grid,” Andrews says.

“Combined with Tarmac’s Ultilayer polymer-modified binder course, this delivers maximum possible crack resistance and durability.”

An added benefit of installing a SAMI Glasstex solution on motorway projects is speed, Andrews adds. “Work typically has to be carried out at night, which obviously limits the amount of time available. Using Glasstex means the reconstruction depth is far shallower. On the M3 it is just 120-150mm, rather than a minimum 360mm with a standard approach, which obviously saves time and, as a result, construction costs.”

With surfacing work progressing well and half the new gantries installed by the summer, the M3 Smart Motorway project looks to be on target to finish as planned in June 2017.

For more information on companies in this article

Related Content

  • Connect Plus joins Highways Agency’s plea to drivers to take care through road works
    October 30, 2013
    Connect Plus, the design, build, finance and operating company for southern England’s M25 and its adjoining trunk routes, last week joined with the Highways Agency to convey vital messages to drivers passing through road works. The company, a joint venture consisting of Balfour Beatty, Skanska, Atkins and Egis Projects SA, was participating in the Highways Agency Road Worker Safety Week (21-28 October), which aimed to get across to the public some of the dangers road workers face in their work close to fas
  • Rome airport taxiway rebuild work
    May 5, 2020
    Rome airport taxiway has benefited from rebuilding work.
  • Lanes Group praised for helping fast-track UK jam-busting road
    October 16, 2015
    The UK drainage and maintenance specialist Lanes Group has helped deliver the new A453 dual-carriageway in the county of Nottinghamshire, one of England’s worst congestion areas. Main contractor Laing O'Rourke managed the two-and-a-half-year project that included the widened commuter route from Junction 24 of the M1 motorway to the A52 highway in Nottingham city centre at a cost of US$265 million. The new road - named Remembrance Way in honour of the 453 British soldiers who lost their lives in Afgha
  • Testing high performance road markings
    February 9, 2012
    High performance markings are among the safety products used to guide traffic safely, but they must be tested and checked. Patrick Smith reports. Road construction zones, zebra crossings, tunnels and areas with frequent fog are particular focal points with regard to road user safety. This is why manufacturers, authorities and contractors are always eager to use innovative road markings and special studs or, where necessary, lane control devices to assist both drivers and pedestrians in all conditions, parti