Tensar’s Glasstex makes the grade in UK’s Smart Motorway upgrade

A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.
February 27, 2017 Read time: 3 mins
Smart move: Foster Contracting is laying 300,000m2 of Tensar’s Glasstex P100 composite on the M3

A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.

More than 130,000 vehicles use the M3 between Junctions 2 (Thorpe and the M25 motorway) and 4a (Farnborough) every day.

As part of 8100 Highways England’s Smart Motorways programme, the capacity of this congested three-lane section is being increased, with hard shoulders converted to ‘smart’ running lanes.

Construction began on site in January 2015. Asphalt surfacing contractor 2399 Tarmac, working for the principal contractor 1146 Balfour Beatty, is carrying out structural resurfacing of the carriageway as part of the project.

“The road is in poor condition, the result of reflective cracking of the asphalt, due to movement of the underlying layers that are made up of both lean mix concrete and bituminous road base,” says Tarmac project manager Barrie Farquhar. “Repairs were needed to strengthen the road and to prevent further cracking, which could have led to water ingress and further deterioration of the concrete.”

Highways England needed a pavement solution that would reduce initial costs, increase service life, as well as minimise maintenance and future disruption.

Consultant 1397 Aecom had specified asphalt reinforcement in the pavement design. Tarmac, subcontractor Foster Contracting and 340 Tensar International proposed Tensar’s Stress Absorbing Membrane Interlayer (SAMI) Glasstex solution, while supporting the required departure from the standard process.

“The SAMI adds tensile stiffness, increasing pavement strength at low strain and mitigating reflective cracking from both traffic-induced stress and from defects in the underlying pavement structure. It also acts as a moisture barrier,” explains Tensar Highways manager Craig Andrews. “This low-maintenance solution will extend the operating life of the pavement, reducing whole-life costs.”

A total of 300,000m2 of Tensar’s Glasstex P100 composite is being laid by Foster Contracting, on both the northbound and southbound carriageways, along the 26km stretch of road – a total of 52km. This composite of glass yarn grid and paving fabric forms an interlayer between the fractured substrate and the asphalt overlay.

“Glasstex adheres to the underlying pavement structure using a straight run bitumen (160/220 pen) bond coat, with a calibrated spray rate of 1.1kg/m², to activate both stress relief and interlayer barrier functions [as given by BS EN 15381: 2008], with reinforcement provided by the grid,” Andrews says.

“Combined with Tarmac’s Ultilayer polymer-modified binder course, this delivers maximum possible crack resistance and durability.”

An added benefit of installing a SAMI Glasstex solution on motorway projects is speed, Andrews adds. “Work typically has to be carried out at night, which obviously limits the amount of time available. Using Glasstex means the reconstruction depth is far shallower. On the M3 it is just 120-150mm, rather than a minimum 360mm with a standard approach, which obviously saves time and, as a result, construction costs.”

With surfacing work progressing well and half the new gantries installed by the summer, the M3 Smart Motorway project looks to be on target to finish as planned in June 2017.

For more information on companies in this article

Related Content

  • Romania speeds up motorway work, including A1 TENT route
    August 2, 2018
    Romania’s transport ministry has cut red tape to speed up 13 road projects this year. Work was stepped up on around 169km of motorway, including contracts on several projects to complete the A1 motorway. The section between Lugoj and Deva is set for the end of the year. The A1 motorway when finished, will be around 580km and connect the capital Bucharest with the Banat and Crișana regions in the western part of the country. Cities along the route include Pitești, Sibiu, Deva, Timișoara and Arad before
  • On the road to energy efficiency and emissions reduction with IRF
    November 15, 2019
    Global commitments to reduce carbon emissions and simultaneously increase the resilience of critical infrastructure to extreme weather events have placed greater societal expectations on road builders to design and deliver sustainable pavements that are both affordable and scalable.
  • Muscat Airport contract for Cooper
    February 9, 2012
    A huge project in Oman will see a proposed new terminal at Muscat International Airport, which has been budgeted at US$1.17 billion, completed by 2014. It will have the capacity to handle 12 million passengers annually, and further expansions planned by The Ministry of Transport and Communication in three subsequent phases will ultimately boost the airport’s capacity to 48 million passengers annually by 2050.
  • Krohne Optiwave 6300 C takes the guesswork out of silo measuring
    August 3, 2017
    A variety of issues affect accurate continuous level measurement inside cement plants. The most critical concerns are dust, heavy build-ups, low-reflective media and uneven surfaces in conical and/or air-injected silos with internal objects. Now, new frequency-modulated continuous-wave – FMCW - radar technology, combined with high signal dynamics, offers a way to accurately and reliably measure product levels.