Skip to main content

Roadtec machines deliver Alaska runway rebuild

A challenging airport runway project in Alaska has been carried out with the help of Roadtec construction equipment equipped with Topcon machine control systems. Anchorage-based Knik Construction carried out the work at the airport in Yakutat, located in the southeast corner of Alaska. Bounded by the Gulf of Alaska to the South, mountains to the North, and coastal glaciers to the East and West, Yakutat is remote even for Alaska. There are no roads leading in or out and all commerce and access is by air o
January 26, 2017 Read time: 4 mins
Windrow techniques were used when necessary
A challenging airport runway project in Alaska has been carried out with the help of Roadtec construction equipment equipped with Topcon machine control systems.

Anchorage-based Knik Construction carried out the work at the airport in Yakutat, located in the southeast corner of Alaska. Bounded by the Gulf of Alaska to the South, mountains to the North, and coastal glaciers to the East and West, Yakutat is remote even for Alaska. There are no roads leading in or out and all commerce and access is by air or sea.

For the contractor, rebuilding the runway facility for the 5247 Alaska Department of Transportation and Public Funding (ADOT&PF) provided many challenges. The Yakutat Airport Runway Pavement Rehabilitation project required the resurfacing of the 2.48km long by 59m wide runway, as well as resurfacing the 91m taxiway. The work was carried out for the state DOT, which has responsibility for all the airports. The Yakutat Airport (YAK) is a state owned, airport located 6km southeast of the central business district of Yakutat. For the 600 residents of Yakutat, this two-runway facility is critical.

Knik explained that for the project, the runway was divided into three sections. At one end the runway tapered to an elevated 760mm, there was a middle section where two runways intersect that required varied profile milling, and a final section that needed 12.7mm surface milling to remove the texture grooves.

However the four-month project presented a logistical challenge to the contractor. All the heavy equipment, asphalt plant, supplies, and asphalt concrete material had to be shipped via barge, which came to Yakutat once/month, while over 3,000tonnes of asphalt also had to be shipped to the site.

Knik started processing aggregate in March 2016 and began work on the runway on May 1st, with the runway being ready for use at the end of August 2016. However the firm had to carefully plan its shipments, because if anything was forgotten, it would either had to wait for the next barge or be brought in by air. The firm also needed reliable machines, as component failures and machine downtime would have caused further problems.

Knik had a milling crew of three, which operated a 1252 Roadtec RX900e with 3.81m cutting drum. A total of 6,000tonnes of cuttings were removed, which was mixed with 50% D-1 locally-produced aggregate base and reused as fill on the section of the runway that required elevation to alleviate water issues.

Knik explained that because of the remote location, it was beneficial to reuse the cuttings immediately rather than using stockpiling, as otherwise the material might sit for years before it would be used as fill or RAP. To ensure accurate milling depth, the cold planer was equipped with a 342 Topcon GPS machine control package. This system played a crucial role in delivering the precision needed.

For the Yakutat Airport runway, Knik shipped over to the remote location a 400tonne/hour portable double drum Astec asphalt plants, eight belly-dump haul trucks, two Blaw-Knox PF4410 tracked pavers, and two Roadtec SB-2500e Shuttle Buggy MTVs. The MTVs were paired up with the pavers and their use on the project had been specified by the ADOT&PF, so as to ensure the runway would meet specifications.

There were two paving crews with six workers on each, plus eight locally-hired truck drivers. For the most part, the existing runway served as the base for the paving. The asphalt plant was located near the shipping docks. The haul trucks would collect loads and transport them 13km to the material transfer vehicles (MTVs) at the runway site.  

According to Amanda Gilliland,  project manager with Knik Construction,  the two MTVs prevented segregation and kept both pavers productive. In instances where there was insufficient space for the trucks to dump, the belly dump trucks could offload in another area and the Shuttle Buggy would then pick up the piles and transport these back to the paver.

The Yakutat Airport project required 62,000tonnes of HMA, making it the biggest paving project in Alaska for 2016. On a good production day, Knik Construction paved up to 6,000tonnes, leaving the top lift of the runway with few transverse joints. The company also used infrared cameras to scan the freshly paved mat, to confirm that there were no cold spots.

Despite the high rain fall at times, the work was completed to specification and within the tight time schedule required.

For more information on companies in this article

Related Content

  • Volvo trucks on the move at Lummen
    February 29, 2012
    Construction company Jan De Nul is using a fleet of Volvo machines for a key highway project in Belgium. The machines have been able to move 26,000m³/weekend on the project to upgrade a highway junction at Lummen, a small town 60km from Belgian capital Brussels. A fleet of 16 Volvo ADTs is being used for the work, to improve the intersection between the E313 and E314, which had become an accident blackspot. Designed some 50 years ago, the roads provide important links from Leuven, Antwerp and the port of Os
  • Wirtgen slipform paver works in Brazil road contract
    May 15, 2015
    Local contractor Galvão Engenharia opted to use an SP 850 slipform paver from Wirtgen as one of the key machines in the job to upgrade and improve the Anel Viário de Fortaleza. This important highway connects Fortaleza, located in the federal state of Ceará, with the busy port of Pecém. The deepwater port in Pecém is some 60km from Fortaleza and since it was inaugurated in 2002, the city has become a primary port for exporting fruit products in refrigerated containers. Fuel and liquefied gas, fertilizer
  • Chinese quarry increasing size of Caterpillar fleet
    December 10, 2013
    Chinese quarry producer Beijing Xindadi Equipment Company is looking to increase the size of its Caterpillar machine fleet as part of its plan to increase output The company is based at Beijing Miyun Taishi Village and currently produces 1-1.5 million tonnes/year of limestone, which is used for general construction in the Beijing area. Zhang Guofeng is equipment manager for the firm and said, “Business is good because the market is not affected by the downturn.”
  • Chinese plant order for Lintec
    October 6, 2021
    Lintec-Linnhoff has supplied a major Chinese contractor with an asphalt batching plant to meet high output requirements. The contractor required a plant able to deliver over 3000tonnes of asphalt/day to keep pace with strong demand in the area