Beijing airport runway features novel asphalt solution

Beijing ranks amongst the five busiest airports across the globe and its runway surfaces face tough stresses as a result. Over 94 million passengers flew through Beijing Capital Airport (BCA) in 2016 and as many as 70 flights/hour can take off and land during peak times. The 60m-wide middle runway of Beijing Capital International Airport is the busiest of the three runways, with a landing and take-off flight ratio of up to 40%. This runway was first rehabilitated in 1996 and then repaired in 2013 and 2015
December 7, 2017 Read time: 3 mins
Paving in echelon was carried out at Beijing airport, with the project benefiting from Evotherm technology

Beijing ranks amongst the five busiest airports across the globe and its runway surfaces face tough stresses as a result

Over 94 million passengers flew through Beijing Capital Airport (BCA) in 2016 and as many as 70 flights/hour can take off and land during peak times. The 60m-wide middle runway of Beijing Capital International Airport is the busiest of the three runways, with a landing and take-off flight ratio of up to 40%. This runway was first rehabilitated in 1996 and then repaired in 2013 and 2015 to address damaged areas. However in April 2017 major rehabilitation work was carried out, which included pavement milling, paving and light installing. The construction area consisted of 130,000m2 of runway and 70,000m2 of taxiway for a total construction area of 200,000m2.

Paving and maintaining an airport runway is never easy. The ageing issues of most concern are block cracking and fatigue cracking so 8536 Evotherm warm mix asphalt (WMA) technology was selected to help extend the life of the airport’s runway.

Chinese contractor Beijing Sino-Aero Construction Engineering (BSACE) worked with Evotherm to select the right technology for the project. When searching for a product, the focus was maximising compaction and consistency of the mix due to the stiff and difficult-to-compact mixture types on the runway.

Yifan Yang, technical services at Ingevity in China said, “This project lasted for four weeks in April. It required speed in daytime and night-time paving, so that the least amount of disruption to BCA’s traffic occurred.”

“Evotherm was chosen particularly because of the materials used in this project,” said Lennon Dong, structural technical management for Ingevity in China. He said that the airport mixtures resulted in Marshall stability over 14kN at 60˚C, along with rutting resistance of over 10,000 passes/mm when measured with the Chinese wheel rut test. The bottom course applied by BSACE contained a high concentration SBS and an anti-rutting agent, and the wearing course mix was a polymer modified stone matrix asphalt (SMA) mixture with a high concentration SBS, an anti-rutting agent and glass fibre additives.

BSACE had two mix plants set up for the project and Evotherm was added as the tank trucks were unloaded. The runway’s pavement structure consisted of about 50mm of warm SMA surface layer, another 60mm of warm dense-graded middle layer mixture, and 80mm of modified WMA mixture for the bottom layer.

The HMA production temperature reduction allowed the workability of the high viscosity and stiff asphalt mixture used on runway pavement to be improved. Compaction aids were utilised to better cope with the night construction conditions to optimise performance. The technology and methods used allowed for improved adhesion between the asphalt binder and aggregates as well as increasing resistance to water damage. The use of a lower production temperature meanwhile helped to limit binder ageing and improve overall durability. The Evotherm additive was easy to use as it can be added to the asphalt as the asphalt tank trucks are being loaded, while there was no need for any changes to the plant. Production temperatures for the asphalt ranged from 175-185˚C, with paving temperatures from 165-175˚C and compaction temperatures from 150-165˚C.

“Evotherm provided many benefits on this runway project,” said Merlin Zhou, technical marketing management with Ingevity in China. “We saw significant improvement in the workability of high viscosity and stiff asphalt mixtures typically used on runway pavements. We also encountered windy conditions during night paving and found the Evotherm helped greatly with compaction despite the windy conditions.” As an added bonus, BSACE completed the project three days earlier than expected.

For more information on companies in this article

Related Content

  • Porner commissions another Biturox plant for India’s IOCL
    November 24, 2017
    Pörner Group recently handed over to India’s IOCL a Biturox plant that has the annual capacity to supply bitumen for more than 1,000km of road. Pörner and IOCL (Indian Oil Company Limited) commissioned the Biturox bitumen plant located at IOCL’s Barauni Refinery near Patna in eastern India. This is the 4th plant operated by IOCL based on Biturox technology. Pörner again provided the license and engineering services.
  • Tufflayer smooths out the road to Bournemouth, England
    November 29, 2019
    Hanson has laid over 1,000 tonnes of Tufflayer asphalt to extend the life of a section of the A338 Bournemouth Spur Road in southern England.
  • Competitive asphalt compaction market
    February 13, 2012
    Existing tough competition will step up another gear with the launch of further new machines in the asphalt roller market, Mike Woof reports. The asphalt compaction equipment market is intensely competitive, with a number of major firms all fighting to boost market share. And with many major manufacturers having revamped ranges during 2010 and further new models now due, this rivalry is set to become tougher still.
  • Telematics could be an area for John Deere and Wirtgen resource sharing
    April 20, 2018
    The gods were smiling on the Wirtgen Group for the company’s Road Technology Days 2018 event. This year it was held in summer-like weather at the recently expanded Voegele plant near Mannheim in Germany. Within days the season dramatically changed from dreary chilly late winter to high temperatures, just in time to bathe the amassed demonstration equipment and the 4,000 guests in summer sunshine. But there won’t be any such dramatic changes within the Wirtgen Group, according to Domenic Ruccolo. After 28