A new airport project is benefiting from some of the latest developments in compaction technology Work started on a new airport for Istanbul in June 2014, with the facility set to be one of the world's largest and to set new standards when it opens for business.
January 6, 2017 Read time: 3 mins
The rollers operate in a line to help deliver efficient compaction

A new airport project is benefiting from some of the latest developments in compaction technology

Work started on a new airport for Istanbul in June 2014, with the facility set to be one of the world's largest and to set new standards when it opens for business.

172 BOMAG has been playing a key role in the construction work at the new site, which is located close to the Black Sea coast.

The construction equipment company has worked closely with the engineering team on site and BOMAG machines are now carrying out the largest compaction operation in the firm’s history, using over 130 single drum rollers on the project.

The columns of the terminal building have already been erected and provide a first impression of the dimensions to be expected at the new Istanbul airport. Upon completion, it will extend to some 8,000ha.

The construction site of the major airport is located about 35km north-west of Istanbul's centre, on the coast of the Black Sea.

The area, which is a former open pit coal mine, features rugged terrain that has to be levelled. To do this requires the removal of 400 million m3 of soil and filling in any holes on the site. About 13,000 personnel are deployed on the construction site and they work seven days/week in two shifts totalling 20 hours/day. Meanwhile BOMAG machines are playing a key role in the work.

At the beginning of 2015, a fleet of no less than 136 BOMAG BW 226 and BW 216 heavy single drum rollers with padfoot and polygonal drums started operating on the construction site. Of these, 61 are equipped with the Bomag Terrameter (BTM) and 45 with the Bomag Compaction Management 05 (BCM 05) with GPS.

To optimise the process for the roller drivers involved, depending on the type of material, a combination of four padfoot and/or polygon soil compactors drive behind each other on a lane. These are followed by a smooth drum roller that finishes and documents the compaction process.

One of the challenges posed is the daily compaction checks required. With around 2 million m2 being compacted/day, roughly 2,500 individual tests would usually be required. However this would be both costly and time-consuming.

Instead, BOMAG's BCM 05 compaction control system and the BOMAG GPS system are providing a cost-efficient alternative.

These packages monitor the surface and collect all the relevant data. This is then transferred to a central laboratory, which compiles and reads it.

An external consultant responsible for approving the tested areas evaluates the resulting single documents, an average of 20/day, and checks the compaction processes. This provides complete documentation for the site and helps deliver greater operating efficiency overall.

The single drum rollers are still hard at work at the airport site, with the targeted opening of the first phase in February 2018.

For more information on companies in this article

Related Content

  • Concrete plants: flexibility and efficiency
    March 17, 2016
    Concrete mixing plants are becoming more flexible and innovative to ensure they meet increasingly stringent construction schedules. Increasing demands are put on contractors to cut down the transportation of material to construction sites in the name of efficiency and the environment. For that reason concrete mixing plants are increasingly flexible in their transportation to sites, their set up times and their output. Ammann Elba, the company created when German-based Elba was acquired by Ammann in 20
  • Leica Geosystems new machine control tool
    February 7, 2017
    Leica Geosystems is aiming to improve compaction quality with its new machine control tool. The Leica iCON roller package can deliver benefits to both compaction quality and productivity. The package provides the compactor operator with an on-screen visualisation of completed passes, displaying where they have occurred and where more are needed for consistent results. The different colours on the display show the operator where work has been carried and to what degree. Using this system means that costly
  • PERI helping to build world’s longest underwater tunnel
    April 4, 2013
    In China, PERI is playing a crucial role in the construction of the world’s longest underwater tunnel The 6km tunnel is part of a new 35km long road connection across the Pearl River bay in southern China, aiming to allow Hong Kong to grow both physically and economically with Macau and also Zhuhai on mainland China. In a huge field factory near the underwater tunnel site, two production lines are being used to produce a total of 33 tunnel elements. Each of the reinforced concrete tubes for the standard sec
  • GPS guidance delivers accurate machine control
    July 12, 2012
    GPS systems for machine control can make massive reductions in operating costs for contractors. Using GPS systems for machine control can make massive reductions in operating costs for contractors and the pace of technology improvements from manufacturers has been rapid. This market segment is dominated by Leica Geosystems, Trimble and Topcon, all of which introduced an array of new products earlier this year. Topcon's dozer control system first seen in public at the Intermat show in Paris, offers notable c