Transylvanian motorway breaks new ground in engineering

Normally in hilly ground, we would use the excavated soil from the cuttings to fill the valleys," says Bogdan Sgarcitu, External Affairs Manager of construction company Bechtel. "But on this stretch the clay-like soil cannot be compacted, so we've had to use many more piles than normal: in just three months we installed more than 500, some drilled as deep as 24m. We've also had to transport millions of tonnes of materials over some less-than-perfect infrastructure."
July 11, 2012 Read time: 4 mins
Normally in hilly ground, we would use the excavated soil from the cuttings to fill the valleys," says Bogdan Sgarcitu, External Affairs Manager of construction company Bechtel. "But on this stretch the clay-like soil cannot be compacted, so we've had to use many more piles than normal: in just three months we installed more than 500, some drilled as deep as 24m. We've also had to transport millions of tonnes of materials over some less-than-perfect infrastructure."

Bogdan was speaking about the Cluj-Napoca section of the Transylvanian Motorway, a massive 415km, four-lane highway featuring more than 300 bridges, 70 overpasses and 19 interchanges. It is the largest highway project in Europe. When complete in 2013, it will connect central Romania with the country's northwestern border with Hungary. And it will make what is now a tough ten-hour tour into a smooth three-hour breeze.

This sleek new €2.2 billon (US$3 billion) national highway will bring the country's infrastructure in line with that of its new economic partners. The road will ease traffic jams, improve safety, and open up the country to new possibilities for tourism and trade, likely becoming the preferred route between the Black Sea and Western Europe.

4138 Bechtel and 5252 Enka, two leading construction companies, are handling the project together. They brought an existing fleet of 67 178 Caterpillar machines and purchased an additional 68 especially for this project. Now, across the valleys, mountains and plains of Transylvania you can see Cat excavators, dozers, wheel loaders, dump trucks, motor graders, soil compactors, cold planers, wheel pavers and generators.

As part of its regular service to all its customers, local Cat dealer, 2154 Bergerat Monnoyeur, ensures a secure and fast supply of original Cat spare parts and consumables. It also provides a full day's training on-site by an experienced service technician, with every machine's delivery. "Our technicians ensure that the customers' operators know all about the daily inspection and routine servicing," says Mihai Hotinceanu of Bergerat Monnoyeur. "They also give some advanced operator training to help ensure maximum productivity and efficient machine use. "Of course, we cannot train all the operators so we describe these one-day visits as 'train-the-trainer' sessions, the knowledge trickles down to all operators on the job site."


The road to prosperity

Road building is always good news for the local economy: it immediately creates new jobs and new skills in the project itself as well as driving demand for supporting products and services throughout the nation. But the sheer scale of this project represents a massive injection of energy into the Romanian economy. Currently, more than 3,000 Romanians (93% of the project team) are working on the motorway, and in 2010, at the peak of construction, that number will exceed 8,000.

When the road fully opens in 2013, it will be a powerhouse for Romania's economic development as it will open trade routes from central Romania to its European and Central Asian neighbours. In addition, the country is already gearing up for an expected 30% increase in tourism and many analysts predict that collateral investments will equal that of the motorway's €2.2 billon.

Bridge to the past and the future

Romania is a country with a rich history: not only was the region intensely colonised by the ancient Romans (hence the name: Romania), its history of civilisation stretches many millennia. In fact the oldest modern human remains in Europe were discovered here six years ago. Not surprisingly then, on a jobsite that spans 3,320 hectares the road builders have unearthed some rather special sites of historical interest. So far, 14 archaeological teams have retrieved hundreds of artefacts, and digs around Cluj revealed a 6,500-year-old settlement with huts and coloured pottery. "It's good to remember the past," says Bogdan of Bechtel. "But it's also good to think of the future, and we hope what we're building here will provide progress and prosperity for many years to come."

Preparing the rural communities: School children, herdsmen and other locals are currently receiving road safety awareness training. This is backed up with free reflective bands on school satchels and horse-drawn wagons. The new motorway will pass through rural regions where the local communities live an uncomplicated life. That's why Bechtel and Enka are preparing the locals for the eventual arrival of large amounts of fast-moving traffic. The team has partnered with local traffic authorities on road safety training, and every project driver has taken defensive driving classes. So far, more than 800 Romanian children have learned theoretical and practical lessons in road safety, and 1,000 herdsmen and shepherds have been given reflective vests free-of-charge. Safety crews have even fitted out 100 horses with reflective collars.

For more information on companies in this article

Related Content

  • Rising to the challenge
    July 18, 2012
    Visualise today's concept of a major commercial traffic corridor in the western United States. A roadway responsible for delivering goods to Arizona, Nevada and Utah, that also connects Mexico to the United States to Canada through the North American Free Trade Agreement (NAFTA). What springs to mind? A multi-lane highway carrying thousands of vehicles a day past cities at speeds up to 113km/hour, while egress ramps make sure vehicles get safely to city streets and their final destination. This is not the c
  • Testing high performance road markings
    February 9, 2012
    High performance markings are among the safety products used to guide traffic safely, but they must be tested and checked. Patrick Smith reports. Road construction zones, zebra crossings, tunnels and areas with frequent fog are particular focal points with regard to road user safety. This is why manufacturers, authorities and contractors are always eager to use innovative road markings and special studs or, where necessary, lane control devices to assist both drivers and pedestrians in all conditions, parti
  • 2+1 type roads – a chance to be better in road safety for Lithuania?
    January 14, 2016
    Lithuania is one of the 28 European Union countries which is seeking to have good results in road safety. However, such as wish does not looks like easy achievable. Moreover, to get away from the worst Top 6 countries in EU could not be achieved since 1991 (by the EU road accidents database - CARE).
  • UK motorway bridge work
    June 10, 2025
    A new bridge now spans the UK’s busy M6 motorway.