Building an airport for St Helena

The remote South Atlantic island of Saint Helena will shortly benefit from the construction of a new airport as well as access roads and supporting infrastructure. This is the biggest construction project in the history of the island, which lies nearly 2,000km off the coast of Africa. The airport is expected to boost economic development for the island’s 4,000 residents with an estimated 20,000 people a year forecasted to visit this highly remote, 122km2 equatorial volcanic outcrop. At present the islan
August 29, 2013 Read time: 3 mins
A fleet of Volvo ADTs is being used to carry out the haulage operation for St Helena’s airport project

The remote South Atlantic island of Saint Helena will shortly benefit from the construction of a new airport as well as access roads and supporting infrastructure. This is the biggest construction project in the history of the island, which lies nearly 2,000km off the coast of Africa.

The airport is expected to boost economic development for the island’s 4,000 residents with an estimated 20,000 people a year forecasted to visit this highly remote, 122km2 equatorial volcanic outcrop. At present the island’s only regular transport link is through RMS St Helena, an old 4872 Royal Mail vessel that makes the trip from South Africa once every three weeks.

The project’s client is St Helena’s Government and the work is being funded by the UK’s 3915 Department for International Development (DfID) with the two phases of the project valued at US$371 million. The airport is being constructed on an arid part of the island, the Prosperous Plain, on the north-eastern coast. Phase One will see the construction of the airport and supporting infrastructure, including a 14km-long connecting road to the capital of Jamestown. Phase Two will see the operation of the airport for a period of 10 years, commencing in February 2016.

Construction firm Basil Read is carrying out the work and began by building a temporary rock and concrete jetty in Rupert’s Bay on the North of the island, with mooring points positioned in the bay to allow materials to be off-loaded. The jetty is capable of accommodating the NP Glory 4, Basil Read’s chartered 1,530tonne, the first ocean-going vessel ever to voluntarily touch the island.
The first machine to drive onto St Helena was a Volvo G940B grader followed by Volvo’s 70tonne EC700C excavator and several Volvo articulated haulers, including both the new F-Series A40Fs and an A30E. This fleet joined smaller machines including an EW140C excavator, a BL61B backhoe loader and a DD24 compactor, which had been delivered earlier on the RMS St Helena for preparation work.

Construction workers are carried on the RMS St Helena from Cape Town, a five-day voyage. The contractor moves equipment and materials from Walvis Bay in Namibia on the chartered vessel, an 80m long ocean-going landing-craft fitted with a 40tonne derrick crane and modified to carry one million litres of fuel, plus 1,000tonnes of cargo.

Once complete the concrete runway will be 1,950m long and the terminal building, air traffic tower and fire station will cover an area of some 2,500m2. The contractor is now using four EC700DL excavators, 20 A40F haulers, four A30E hauler-based container carriers, two G940 graders, six A30Es converted to water trucks, two A30E haulers, an EC360B excavator with breaker, a EW140C excavator, four SD200X compactors, a L120F loader and an EC290 excavator.
Each team is using a 70tonne excavator and five 40tonne haulers plus ancillary machines such as graders, dozers and water trucks. At peak times, the teams work six days a week.

Prior to the main equipment being delivered, 359 Volvo CE’s independent South African dealer, Babcock, had service personnel, technicians and parts personnel already in place on the island. Volvo is backing up this team with a technical supervisor for the project. A second delivery by the freighter NP Glory 4

landed a further 15 Volvo A40F articulated haulers, three additional Volvo EC700C excavators and three SD200DX single drum soil compactors.

For more information on companies in this article

Related Content

  • The power of water
    July 18, 2012
    The popularity of hydrodemolition is growing worldwide and was the specified solution for work on two vital Swedish links The hydrodemolition technique, which uses high pressure water jets to remove damaged concrete from various structures, is playing a crucial role in the major restoration of the vital Central Bridge and Söderled Tunnel in the centre of Sweden's capital Stockholm. The 1,550m dual two-lane rectangular box Söderled Tunnel and connecting dual two and three-lane Central Bridge are a vital 2.6k
  • Shantui wins Africa equipment deals
    May 5, 2015
    Chinese firm Shantui has won an order for one of its compaction units from a customer in Algeria, while developing its operations in Angola An SR32R trash compactor was shipped from Shantui’s production facility in Jining, Shina to the customer in Algeria and the unit is said to be performing well. The company claims that reliability, durability, productivity and ease of maintenance are all features of this model. Shantui has supplied five of these units to North African customers over the past 12 m
  • Challenging Colombian tunnel completed
    May 30, 2024
    A tunnel stretch on Colombia’s Santa Fe - Cañasgordas highway is complete – Mauro Nogarin reports
  • Crane assembly for Tibet excavator
    February 9, 2017
    A tough machine assembly operation at extreme altitude has been carried out by two cranes from XCMG The cranes were used to assist in the assembly of a large excavator needed to assist in production at an extraction operation in Tibet. Located at an altitude of no less than 5,400m on the very remote Mila Mountain, the extraction sites was aiming at upgrading its operations and boosting productivity with the addition of a new 100tonne class excavator. The two cranes, an XCT100 model and a QAY300A machi