Piers completed for Morandi Bridge replacement project

The last of the 18 elliptical 40m-tall piers have been finished.
By David Arminas February 20, 2020 Read time: 2 mins
In total, 19 spans will eventually cradle a continuous steel deck (photo courtesy Salini Impregilo/PerGenova)

PerGenova, the joint-venture constructing the new Genoa Bridge, recently completed the last of the 18 elliptical piers – 40m-tall giants of reinforced concrete.

PerGenova – consisting of Salini Impregilo and Fincantieri – said that it reached the milestone in record time. At the moment, 10 of the 94m-long spans of the deck that will rest on the piers have been installed. In total, 19 spans will eventually cradle a continuous steel deck.

The spans needed to be raised more than 40m into the air and placed atop the piers. Also raised were 14 sidings that resemble wings along the side of the bridge, as well as fittings such as the sections that will facilitate the pouring of concrete. In light of the span’s weight, cranes were not used. Instead, strand jacks were brought it and used cables to hoist the span into place at a speed of 5m per hour.

The bridge replacement work follows the collapse of the old Morandi Bridge in 2018, causing fatalities. The new bridge also represents Progetto Italia, led by Salini Impregilo. The vision is for a new way of building complex infrastructure in Italy where private companies and public institutions come together to develop projects on time and to budget. The goal is to unblock stalled projects and to create innovative ways of working, according to Salini Impregilo.

“This [new bridge] is a unique project from a number of vantage points: there is the innovation and sustainability aspect, the speed at which the bridge is being built, the close public interest and the pressure that comes with it, the attention to quality and safety and, obviously, the very reason for the bridge to come into existence,” said Pietro Salini, chief executive of Salini Impregilo.

The project has up to 600 people working on site daily and more than 1,000 when including the supply chain. Progress can be followed in real time thanks to live streaming at the website www.pergenova.com which gets a round-the-clock feed from eight webcams.

For more information on companies in this article

Related Content

  • Egypt’s canal tunnel project
    May 16, 2018
    Major progress is being achieved on Egypt’s key tunnel project, a link that runs underneath the Suez Canal.
  • High reach excavator safety training launched
    April 11, 2012
    New demolition tolls are coming to market while safety training for high reach excavator operators has been establishe.d With the Intermat equipment exhibition due shortly, various manufacturers are offering new demolition tools to the market. Meanwhile the UK's National Federation of Demolition Contractors (NFDC) is now setting a lead in the sector by offering a high reach excavator training course. The NFDC has partnered with the National Demolition Training Group (NDTG) to develop the world's first train
  • High reach excavator safety training launched
    April 13, 2012
    New demolition tolls are coming to market while safety training for high reach excavator operators has been established With the Intermat equipment exhibition due shortly, various manufacturers are offering new demolition tools to the market. Meanwhile the UK's National Federation of Demolition Contractors (NFDC) is now setting a lead in the sector by offering a high reach excavator training course. The NFDC has partnered with the National Demolition Training Group (NDTG) to develop the world's first train
  • Tekla models its BIM software
    January 30, 2015
    More and more design and construction of infrastructure, from buildings and power plants to highways are using building information modelling software. BIM is increasingly the must-have ability for a supply chain and Tekla Structures Construction Modeling software allows concrete contractors to be part of the 3D BIM model.