Piers completed for Morandi Bridge replacement project

The last of the 18 elliptical 40m-tall piers have been finished.
By David Arminas February 20, 2020 Read time: 2 mins
In total, 19 spans will eventually cradle a continuous steel deck (photo courtesy Salini Impregilo/PerGenova)

PerGenova, the joint-venture constructing the new Genoa Bridge, recently completed the last of the 18 elliptical piers – 40m-tall giants of reinforced concrete.

PerGenova – consisting of Salini Impregilo and Fincantieri – said that it reached the milestone in record time. At the moment, 10 of the 94m-long spans of the deck that will rest on the piers have been installed. In total, 19 spans will eventually cradle a continuous steel deck.

The spans needed to be raised more than 40m into the air and placed atop the piers. Also raised were 14 sidings that resemble wings along the side of the bridge, as well as fittings such as the sections that will facilitate the pouring of concrete. In light of the span’s weight, cranes were not used. Instead, strand jacks were brought it and used cables to hoist the span into place at a speed of 5m per hour.

The bridge replacement work follows the collapse of the old Morandi Bridge in 2018, causing fatalities. The new bridge also represents Progetto Italia, led by Salini Impregilo. The vision is for a new way of building complex infrastructure in Italy where private companies and public institutions come together to develop projects on time and to budget. The goal is to unblock stalled projects and to create innovative ways of working, according to Salini Impregilo.

“This [new bridge] is a unique project from a number of vantage points: there is the innovation and sustainability aspect, the speed at which the bridge is being built, the close public interest and the pressure that comes with it, the attention to quality and safety and, obviously, the very reason for the bridge to come into existence,” said Pietro Salini, chief executive of Salini Impregilo.

The project has up to 600 people working on site daily and more than 1,000 when including the supply chain. Progress can be followed in real time thanks to live streaming at the website www.pergenova.com which gets a round-the-clock feed from eight webcams.

For more information on companies in this article

Related Content

  • LiuGong 900E excavators “very key” for company future
    April 16, 2013
    A senior LiuGong figure says the company’s keenly awaited 900E Series excavator is a “very key machine” for its future. Dave Beatenbough, vice president of the Chinese construction equipment manufacturing giant’s research and development arm, said production of the model at LiuGong’s Dressta base in Poland was expected to begin “within three months”.
  • Montreal’s new Champlain Bridge is in a race against time
    June 8, 2018
    Montreal’s US$3.24 billion Champlain Bridge across the St Lawrence River may not be open on time, according to a report by the independent Auditor General. The 3.4km cable-stayed bridge has two decks supporting three lanes of highway traffic in each direction. A third, central deck supports a mass transit system and a multi-use path. The new bridge will replace the nearby 50-year-old Champlain Bridge which has been deteriorating at an alarming rate. The government signed a contract in 2015 with a private
  • A titan of a barrier gate from SMA
    February 4, 2022
    The Titanus barrier gate from SMA Road Safety is ideal for areas characterised by a reduced length opening section.
  • 48 hours re-opening
    July 6, 2012
    Using demolition tools from Atlas Copco helped to maximise productivity on a highly time-sensitive project in Germany. The A3 autobahn runs from the Dutch/German border through the western part of the Ruhr area, the Cologne area, the Rhine-Main area and Bavaria down to the Austrian border at Stuben. It is one of the most heavily used highways in Germany and because of increasing traffic volumes, widening the road to six lanes has become necessary.