Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • Strong exhibitor support for World of Asphalt 2016
    October 16, 2015
    Strong exhibitor support has been noted for the World of Asphalt 2016 exhibition being held next year in the US state of Tennessee.
  • First-time exhibitor CMS Cepcor to display replacement crusher spare parts/crusher liners
    March 11, 2013
    First-time exhibitor CMS Cepcor will exhibit its range of replacement crusher spare parts and premium crusher liners at bauma 2013. Recently awarded the Queen’s Award for Outstanding Achievement in International Trade, CMS Cepcor currently exports to over 100 countries. Despite the worldwide economic recession and credit crisis, the company says its sales turnover increased by over 100% since 2010. “This growth has been achieved through a focus on optimisation of web presence together with an engineering f
  • New conference plans for European road directors
    October 30, 2013
    Plans are in hand for the Conference of European Directors of Roads (CEDR). This event is now run every four years, with this next CEDR conference being the third to be held. The governing board for CEDR held a meeting in Helsinki and the Road Directors’ association reviewed the final report on the implementation of its previous strategic plan and the formalisation of its next. The CEDR strategic plan 3 (SP3) is to develop the priorities and targets for its next cycle. Each SP determines the structuring an
  • Cap Minerals shows EmiControls V12 dust controller
    January 6, 2017
    Distributor Cap Minerals is showing the latest model of the V12 dust controller, whose manufacturer is EmiControls by TechnoAlpin. Applications include working with primary crushers and stockpiles as well as in construction and demolition. The machine can be put on wheels or even mounted on a tower. The V12 sends out a fine water spray to keep the dust down and it can control dust across a distance of up to 50m, said Cap Minerals. The high-performance fan oscillates vertically and horizontally for optimum c