Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • AGS demonstrates the power of its new 3D application for the ID4 anti-collision crane safety management system
    March 27, 2013
    Crane and site safety management specialist AGS, which also makes and supplies elevated obstruction lighting , anemometers and anti-collision systems, will use Bauma to demonstrate its new 3D application for the ID4 anti-collision crane management system. AGS has more than 5,000 systems in use on construction sites around the world and it has a long-term strategic partnership agreement with Bouygues Construction. The group will also announce the setting up of three new subsidiaries in Rhône-Alpes, Île-de-Fr
  • Fraccaroli & Balzan targets large quarries with its new filter press
    January 6, 2017
    Fraccaroli & Balzan, which designs, manufactures and installs waste water treatment systems, is showcasing its biggest filter press yet at bauma 2013. Previously the Italian firm only made lateral beam-type filter presses, which can only go up to a certain size and capacity. Now Fraccaroli & Balzan has developed high beam filter presses, which can be much larger and designed for quarries that need to process high volumes of material. “This filter press is for big quarries with big production that prefer to
  • Fraccaroli & Balzan targets large quarries with its new filter press
    April 19, 2013
    Fraccaroli & Balzan, which designs, manufactures and installs waste water treatment systems, is showcasing its biggest filter press yet at bauma 2013. Previously the Italian firm only made lateral beam-type filter presses, which can only go up to a certain size and capacity. Now Fraccaroli & Balzan has developed high beam filter presses, which can be much larger and designed for quarries that need to process high volumes of material. “This filter press is for big quarries with big production that prefer to
  • Third stage of Sydney’s WestConnex tunnel to be 1km longer
    December 4, 2014
    Changes to the third stage of the planned WestConnex motorway have been announced by Duncan Gay, Roads Minister of Australia’s New South Wales state. The motorway tunnel will be 8km, around 1km longer than initially announced under the US$9.7 billion WestConnex project of 33km of new roads around the city of Sydney. The changes are not likely to cost more, according to the NSW government. The third stage would cover the route between Haberfield and St. Peters and be constructed between 2018 and 2023.