Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-w
October 18, 2018 Read time: 3 mins
The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right (photo courtesy WSDoT)

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, 914 Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an ageing 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, Key Project Report, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened, likely this fall.

Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners is a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems.

For more information on companies in this article

Related Content

  • Morgan’s FireMaster FireBarrier 135 boosts tunnel protection
    January 6, 2015
    Morgan Advanced Materials says its new FireMaster FireBarrier 135 sprayed refractory cement offers superior fire protection and simple, cost-effective installation. The 135 is ideal for concrete tunnel lining and ventilation shafts, escape tunnels and refuges as well as critical systems such as water mains and communication cables.
  • A thousand birthday greetings for US-Canada Thousand Island Bridge
    August 21, 2018
    The Canada-US Thousand Island Bridge system celebrated its 80th birthday in August with presentations and an open house at its US headquarters. The 33.7km three-bridge system over the St Lawrence River took 16 months to build and was completed 10 weeks ahead of schedule. It runs from Collins Landing near Alexandria Bay in the US state of New York to the small town of Ivy Lea in the Canadian province of Ontario. The system connects US Interstate 81 and Canada’s Highway 401, a major motorway between Montre
  • Astec test fires 250th burner
    July 17, 2012
    Astec has test-fired the 250th burner manufactured since entering the burner market in 2003. Astec, an Astec Industries company, built the 150-million BTU/hr gas-and-oil-firing Phoenix Talon burner for Illinois-based Gallagher Asphalt Corporation. The company says its burners offer the latest in reliable burner technology combined with complete one-source responsibility, and it is able to offer everything from a simple burner replacement to a complete installed system, including retrofit installations.
  • New East Africa highway connecting Kenya, Tanzania, South Sudan
    June 8, 2016
    East African countries continue to implement a road Master Plan developed jointly under the East African Community initiative and which aims at integrating the region’s transport corridors to meet the growing demand for road transport by the increasing intra-regional trade and vehicular traffic. Kenya has for example unveiled a US$280 million road rehabilitation project to improve its links with Tanzania and South Sudan with the backing of the African Development Bank (AfDB). Rehabilitation of the 172