Work is progressing on a £320 million (e385 million) project to upgrade a busy 18km stretch of the main A80 Glasgow-Stirling road in Scotland to motorway standard. The project, between the villages of Stepps and Haggs, is part of a massive infrastructure investment in Scotland's transport network, and construction work includes almost 8km of new dual-lane motorway and hard shoulders between
February 17, 2012 Read time: 4 mins
Harsco Infrastructure is playing a vital role providing specialist systems for the A80 upgrade in Scotland
Work is progressing on a £320 million (e385 million) project to upgrade a busy 18km stretch of the main A80 Glasgow-Stirling road in Scotland to motorway standard.

The project, between the villages of Stepps and Haggs, is part of a massive infrastructure investment in Scotland's transport network, and construction work includes almost 8km of new dual-lane motorway and hard shoulders between; 2.7km of the existing A80 road upgraded to three-lane motorway; and almost 7.3km of the existing A80 upgraded to dual-lane motorway with hard shoulders and climbing lanes.

Work on the project has required extensive demolition and reconstruction on existing structures along the route, including the widening of existing bridges and construction of new ones. This is complicated because as a vital arterial route across Scotland's most densely populated region, the road must remain in use throughout the construction period.

1483 Harsco Infrastructure is playing a vital role providing specialist access, formwork and falsework systems.

Concrete and civil engineering specialist 2805 T Mac Construction is carrying out all the on-line work, constructing new bridges and extensions to existing bridges on the main route, some 16 structures.

T-Mac was awarded the subcontract via a traditional competitive tender process and part of its winning bid was a methodology developed in partnership with Harsco Infrastructure, to minimise disruption on the A80 by closing off the hard shoulder and slow lane.

The work requires a varied approach to access and formwork. This not only entails considerable health and safety risk, but also imposes significant logistical and design problems. The safety challenges have been met by using Harsco Infrastructure's equipment to create an enclosed working area to isolate the workforce from the traffic, which presents challenges as space within the route is limited.

"We are utilising a variety of systems from our portfolio to offer workable and time saving solutions" says David Hancock, sales manager for Harsco Infrastructure.

CUPLOK and MkII Soldier Falsework components are used to create a safe hydrodemolition deck under each bridge which serves as a working platform, as well as access for steel-fixing operatives before the introduction of falsework for the new in situ concrete.

"Essentially, the work involves hydrodemolition to break out existing concrete to expose the steel reinforcement before erecting formwork, stitching in the new rebar and casting the bridge extensions," explains T-Mac managing director Mike Traynor.

The newly-widened carriageways, the existing bridge cantilevers and RC bridge beams are partially demolished and new ones cast. The bridge cantilevers are then extended at either side of the decks and new parapets formed. The central sections of the carriageway are also being strengthened by casting new in situ concrete beams and in situ soffits.

"We planned this project for months in conjunction with the main contractor and sub-contractor to ensure the correct solutions for each individual structure. This included the use of our MULTIFORM parapet brackets, for on-line as well as off-line bridge structures," said Hancock.

T-Mac also used the TOPEC soffit panel system supported by modular aluminium GASS legs for the soffit stages on the existing structures reinstatement, due to extremely restricted work space on these structures.

"TOPEC allows the contractor to fit large soffit areas of completed falsework by simply lifting the aluminium panels into place because they are lightweight. Traditional falsework solutions would have required prolonged work in a confined space for both erecting and striking the system," said Hancock.

The original plan was to complete all the extension work on the southern (westbound) carriageway, then switch to the northern (eastbound) side and then travel back to Haggs, carrying out bridge strengthening work along the central reserve. However, the need to adapt to unforeseen circumstances has resulted in a flexible working regime and the methodology has altered slightly.

"This project has demanded the highest possible level of planning, engineering, design and logistics. In January 2010 we had the worst winter weather for several years, with record low temperatures and heavy snow but although the project suffered delays, the contractors have managed to adapt to the conditions and the final completion date has not been affected. The meticulous planning has paid off," Hancock added.

For more information on companies in this article

Related Content

  • Tunnel construction benefits from improved visibility
    November 14, 2012
    Major new tunnel construction projects will, on completion, help secure more reliable journey times for hundreds of thousands of people across the world. Meanwhile, as Guy Woodford reports, leading ITS solution companies have been providing vital equipment for major road tunnels The Martina Tunnel Boring Machine (TBM), a 4,500tonne Herrenknecht Earth Pressure Balance Shield said to have a world record diameter of 15.55m, has required just under a year to build the first of two tunnel tubes for the 2.5km lon
  • Challenges and investment opportunities in East Africa transport infrastructure Sector
    November 21, 2014
    East Africa offers considerable potential for transport infrastructure expansion and investment - Shem Oirere reports Infrastructure, infrastructure and more infrastructure is what is needed to make East Africa the favoured destination and Kenya, Tanzania, Uganda and Rwanda have unveiled grand plans to enhance the infrastructure both nationally and regionally.” This is how market analyst Deloitte introduced its 2014/15 budget analysis for the four countries in July.
  • An IKEA trip for the UK’s NM Group - North Midland Construction
    April 17, 2018
    The UK’s NM Group - North Midland Construction - completed its first contract for iconic furniture retailer IKEA at the Swedish group’s flagship Sheffield store. The nearly-31,600m² store cost €68 million to build and created 480 jobs. The retailer’s most sustainable store to date, it incorporates photovoltaic panels and rainwater harvesting as well as linking to a district heating scheme.
  • Foundations for Mexico highway with help from Liebherr
    November 9, 2017
    A Liebherr rotary drill rig and oscillator combination has been working in Mexico on a highway project for contractor Mota-Engil. A Liebherr piling rig is playing an important role on a major Mexican highway construction project being carried out by a division of the Portuguese firm Mota-Engil. The use of the rig by Mota-Engil Mexico’s newly formed geotechnical division is helping to set new quality standards for piling in the country. The contractor is leasing one of the latest Liebherr LB 24-270 rotary