Upgrade for Medieval bridge

One of the most demanding and challenging impressed current cathodic protection (ICCP) projects ever undertaken by specialist main contractor Concrete Repairs Ltd (CRL) is being carried out on Bideford Longbridge in County Devon, UK. The 24-span medieval masonry arch bridge spans 190m over the tidal estuary of the River Torridge.
February 29, 2012 Read time: 2 mins
Bideford Longbridge, the 24-span medieval masonry spans 190m over the River Torridge
One of the most demanding and challenging impressed current cathodic protection (ICCP) projects ever undertaken by specialist main contractor 3416 Concrete Repairs Ltd (CRL) is being carried out on Bideford Longbridge in County Devon, UK.

The 24-span medieval masonry arch bridge spans 190m over the tidal estuary of the River Torridge. Each span varies from 6.5m to 11m, and this is thought to be because the masonry bridge was built around the original timber bridge whose spans were dictated by the length of timber available at the time. During its lifetime the bridge has been widened a number of times to accommodate the changing nature and density of traffic flows. The last widening was completed in 1928 when reinforced concrete cantilever sections were added to each side of the masonry arches.

Following a structural assessment in 2006, Devon County Council identified 21 weakened cantilevers and the onset of corroding steel reinforcement, caused as a result of high chloride levels and lack of concrete cover. A 3tonne weight restriction was applied while various long term renovation solutions to safeguard the bridge were considered.

CRL was awarded the council contract to repair the concrete cantilevers in September 2008. The £2m project (E2.34 million) is particularly testing due to the combination of ICCP anode systems comprising mixed metal oxide coated titanium mesh and discrete mixed metal oxide coated titanium tubular anodes to ensure a uniform current distribution.

At the same time, the partial demolition and reconstruction of reinforced concrete elements is being carried out and a new underbridge lighting system is being installed, all of which is taking place from restricted scaffold access and in a tidal environment. The project is scheduled for completion in October 2009.

For more information on companies in this article

Related Content

  • Historic bridge upgrade in Minneapolis
    July 28, 2022
    A historic bridge upgrade in Minneapolis is close to completion.
  • Wolffkran leads the pack
    December 10, 2024
    At present, the two WOLFF 7534.16 Clear cranes are drawing a lot of attention near Horb in Germany’s Neckar Valley
  • Germany's advanced bridge construction
    February 24, 2012
    The A98 single-lane motorway in Germany is being extended by a second pair of lanes. Work began in 2007 and required building a second bridge at Rheinfelden in the south-west of the country, parallel to the existing bridge, and identical in design and construction.
  • VST used on Portuguese bridge
    February 17, 2012
    PERI says that its new VST heavy-duty shoring tower serves as load-bearing scaffold for the large bridge and civil engineering projects. Each leg on the VST (VARIOKIT Shoring Tower) system can carry a load of around 600kN (the weight of about 60 VW Golf cars or one Leopard-2 tank), and the extremely flexible modular system can be assembled as segmental sections, towers or shoring tower frames for heights up to 40m.