Road widening means bridge demolition

Two heavy Atlas Copco hydraulic breakers have been used to demolish a bridge on the A40 autobahn at Junction 28 in Gelsenkirchen-Süd, Germany. The bridge was used to carry the four lanes of the A40 over the B277 main road. As the key route in the Ruhr district, the A40 is being widened to incorporate six lanes, so the old bridge needed to be demolished.
February 24, 2012 Read time: 2 mins
Two heavy 161 Atlas Copco hydraulic breakers have been used to demolish a bridge on the A40 autobahn at Junction 28 in Gelsenkirchen-Süd, Germany. The bridge was used to carry the four lanes of the A40 over the B277 main road. As the key route in the Ruhr district, the A40 is being widened to incorporate six lanes, so the old bridge needed to be demolished.

Viersen-based Prangenberg & Zaum had only two days to complete the demolition, commissioned by 945 Strabag. The contractor has a number of Atlas Copco breakers in its fleet and opted to use heavy-duty hammers from the firm for the demolition work, a 7tonne HB7000, a 5.8tonne HB5800 and a 2.5tonne HB2500. Using these tools the solid reinforced concrete bridge and bridge heads were removed in about 32 hours. A pulveriser crushed the demolition waste while it was still on site and the waste was then transferred to Prangenberg & Zaum's recycling station for further processing. The total volume of the demolition project was 2,300m3 of concrete with steel reinforcement and the breakers performed reliably while carrying out the work.

The A40 runs from Straelen on the Dutch border, over the Rhine and across the Ruhr region to Dortmund and is the main arterial road in the Ruhr. Around 120,000 vehicles/day travel around the city of Bochum at peak times, meaning the A40 carries the heaviest traffic in the Ruhr region.

Work on gradually widening the motorway to six lanes was begun in 2010 and should be completed in 2012.

For more information on companies in this article

Related Content

  • Regensburg road revamp will widen key stretch
    February 14, 2018
    Work is now commencing on widening a stretch of the A3 Autobahn where it passes through the Bavarian city of Regensburg. The 15km section of the A3 will be widened from its present two lanes to three lanes. The project is costing €270 million and will be carried out on the section from the junction between the A3 and B8 at Rosenhof to the east of Regensburg and running 15km westwards, past the junction with the A93 Autobahn route that connects with the A9 and Munich to the south. This work is needed as the
  • Caterpillar is offering improved hydraulic breakers
    June 10, 2019
    Caterpillar is now offering its new GC S Series top-mount, hydraulic, silenced hammers. The firm says that its H115 GC S, H120 GC S, H130 GC S, and H140 GC S models are specifically designed for use with hydraulic excavators weighing from 13-40tonnes. The firm says that the new GC S Series models combine high power-to-weight ratios with simple design. The units are said to be robust, reliable and easy to maintain, suiting duties in general construction, demolition and quarrying. Caterpillar-designed hydrau
  • Italian highway bridge and tunnel link
    June 20, 2022
    A project in Central Italy is seeing the construction of new tunnel stretches, a bridge and a viaduct. The work is being carried out on State Road 318 by BESIX in partnership with DONATI, close to Perugia in Umbria.
  • Stable site
    July 23, 2012
    A Wirtgen soil stabilisation machine has been treating a 100,000m2 site in Staffordshire for an advanced logistics centre, a project including access roads and parking areas. The WR2500S recycler is being used to prepare the way for the vast Blue Planet complex in Chatterley Valley, Newcastle-under-Lyme. Throughout the preliminary groundworks the Wirtgen machine, purchased by Barton Plant of Kettering, Northamptonshire, has placed between 6-7,000m2/day of lime/cement stabilised earth on the project, for mai