Peri has Polish bridge covered

A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
February 6, 2012 Read time: 3 mins
A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used.

Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.

The individual sections of the superstructure are concreted directly together here and connected by means of tensioning cables. Subsequently, the hardened bridge section is raised a few millimetres and moved forward together with the other finished segments by one cycle length in the direction of the bridge's longitudinal axis.

Prefabrication of the individual repetitive bridge sections is being carried out with a stationary formwork, and a temporary protection roof, based on the 298 PERI UP modular scaffold, spans the working area and allows weather-independent construction of the individual sections for the superstructure.

According to the German formwork manufacturer this is one of the factors that allowed the 2296 Skanska-1547 NDI Joint Venture to reduce the construction period by three months.

For concreting work on the hollow box profile, a construction time of a year was originally planned, and as work started in November 2009, minimum temperatures of up to -25°C were expected during the winter.

To cater for the weather, the contractor planned the temporary protection roof for the construction phase: the possibility of renting the LGS (lattice girder system) protection roof for the period of use provided an economical solution.

Altogether, the jobsite team is using four roof structures: two smaller, permanently installed tents are used for reinforcement work preparations, while two movable protection roofs on basis of the LGS span the formwork and concreting areas.

To ensure unhindered material and concrete installation, the design allows the protection roofs to be moved. The girder supports are equipped with 55.5m long rails, which are over twice as long as the protection roofs and which are easily moved by two to four people. The wheel allows the roofs to be moved in a longitudinal direction.

"At the level of the girder, the static system of a single-span beam with one stationary and one movable support can be realised without any problems by means of system components," says PERI.

The spatial arrangement of the two sets of incremental launching equipment gave the position for the weather protection roofs: the available space between the formwork for both lanes was very limited. Load transfer of the support construction of both weather protection roofs had to be guaranteed via a common central support.

"With Keder track and sheeting, the scaffold constructions result in very light and translucent roofs. The solution in Grudzi?dz also includes a side and gable covering. "Overlapping of the sheeting at all joints ensures a tightly-fitting enclosure which at the same time can easily be opened. With extremely low outside temperatures, the temporary tents were also heated.

"An additional positive effect of the enclosure is the consistently high concrete quality achieved throughout due to the constantly good setting process."

For more information on companies in this article

Related Content

  • REBLOC 100SFP_8 ensures highest safety on bridges
    May 22, 2019
    Concrete barrier expert REBLOC has developed REBLOC 100SFP_8, a powerfully flexible barrier system for new bridges as well as for bridge refurbishment. Tested freestanding, the barrier achieves containment levels H2 with working-width W3 and H4b with W5. It is also possible to achieve H4b with W4 by using an additional position securing system. The safety concrete barrier is part of the REBLOC SWITCH product line which enables the use of the same system as either a temporary or a permanent barrier. All s
  • 2010 GRAA Winner Profiles
    February 13, 2012
    Our series of profiles on winning projects from the 2010 Global Road Achievement (GRAA) Awards continues with the Construction Methodology Category won by Barrier Systems/Utah Department of Transportation With any major road construction project, the disruption of traffic flow is of paramount concern for engineers, workers and travellers, particularly as it relates to increased traffic delays and the safety of those driving through the work zone.
  • Doka puts the ‘Y’ in Turkey
    July 8, 2020
    The 600m cable-stayed Kömürhan Bridge rises around 165m over eastern Turkey’s Karakaya Dam Lake and is part of the Malatya-Elazig State Highway. The bridge is the fourth single-pylon cable-stayed bridge in the world and is due to open in July.
  • New software makes road marking applications easier
    February 17, 2012
    Equipment, materials and testing combine to offer motorists better road markings as Patrick Smith reports Drivers realise that clear road markings, particularly in darkness and during the wet, are life-savers, offering guidance and direction. Manufacturers of marking materials, in-road studs, and testing and laying equipment have spent years perfecting solutions to make such markings easier to place; easier to see through the use of a variety of materials, and longer lasting. Sophisticated testing equip