Peri has Polish bridge covered

A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
February 6, 2012 Read time: 3 mins
A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used.

Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.

The individual sections of the superstructure are concreted directly together here and connected by means of tensioning cables. Subsequently, the hardened bridge section is raised a few millimetres and moved forward together with the other finished segments by one cycle length in the direction of the bridge's longitudinal axis.

Prefabrication of the individual repetitive bridge sections is being carried out with a stationary formwork, and a temporary protection roof, based on the 298 PERI UP modular scaffold, spans the working area and allows weather-independent construction of the individual sections for the superstructure.

According to the German formwork manufacturer this is one of the factors that allowed the 2296 Skanska-1547 NDI Joint Venture to reduce the construction period by three months.

For concreting work on the hollow box profile, a construction time of a year was originally planned, and as work started in November 2009, minimum temperatures of up to -25°C were expected during the winter.

To cater for the weather, the contractor planned the temporary protection roof for the construction phase: the possibility of renting the LGS (lattice girder system) protection roof for the period of use provided an economical solution.

Altogether, the jobsite team is using four roof structures: two smaller, permanently installed tents are used for reinforcement work preparations, while two movable protection roofs on basis of the LGS span the formwork and concreting areas.

To ensure unhindered material and concrete installation, the design allows the protection roofs to be moved. The girder supports are equipped with 55.5m long rails, which are over twice as long as the protection roofs and which are easily moved by two to four people. The wheel allows the roofs to be moved in a longitudinal direction.

"At the level of the girder, the static system of a single-span beam with one stationary and one movable support can be realised without any problems by means of system components," says PERI.

The spatial arrangement of the two sets of incremental launching equipment gave the position for the weather protection roofs: the available space between the formwork for both lanes was very limited. Load transfer of the support construction of both weather protection roofs had to be guaranteed via a common central support.

"With Keder track and sheeting, the scaffold constructions result in very light and translucent roofs. The solution in Grudzi?dz also includes a side and gable covering. "Overlapping of the sheeting at all joints ensures a tightly-fitting enclosure which at the same time can easily be opened. With extremely low outside temperatures, the temporary tents were also heated.

"An additional positive effect of the enclosure is the consistently high concrete quality achieved throughout due to the constantly good setting process."

For more information on companies in this article

Related Content

  • The Cebu–Cordova Link Expressway
    September 19, 2021
    The 8.5km CCLEx, as it is known, will include the longest and tallest bridge in the Philippines when the structure is finished next year
  • 'Blinding success' at Welsh quarry
    February 14, 2012
    Wales is renowned for many things but dry weather is not one of them. A combination of being close to the Atlantic and having lots of mountains means that it rains a lot and this is bad news when fine screening limestone using conventional steel wire mesh, which tends to clog and blind over in damp weather.
  • Steel sealed on Stonecutters Bridge
    February 6, 2012
    The stone mastic asphalt surface being laid on the bridge deck. The Stonecutters Bridge in Hong Kong, the second longest spanning cable stayed bridge in the world, is a dual three-lane crossing of the Rambler Channel. It utilises 33,500tonnes of structural steel in the bridge deck; 32,000m3 of concrete in the towers and 65 steel deck units relying on 224 cables. Effectively protecting the megastructure's deck from the weather extremes (monsoon rains and extreme heat in the summer) and the high levels of tra
  • Costa Rica concrete repairs
    February 15, 2012
    Work has started on the long awaited San Jose-Caldera Highway in Costa Rica, following numerous delays and setbacks. The new 77.5km highway will be used daily by more than 81,000 vehicles, reducing the travel time between the Central Valley and the Central Pacific Coast by at least 30 minutes.