A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
February 6, 2012 Read time: 3 mins
A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used.

Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.

The individual sections of the superstructure are concreted directly together here and connected by means of tensioning cables. Subsequently, the hardened bridge section is raised a few millimetres and moved forward together with the other finished segments by one cycle length in the direction of the bridge's longitudinal axis.

Prefabrication of the individual repetitive bridge sections is being carried out with a stationary formwork, and a temporary protection roof, based on the 298 PERI UP modular scaffold, spans the working area and allows weather-independent construction of the individual sections for the superstructure.

According to the German formwork manufacturer this is one of the factors that allowed the 2296 Skanska-1547 NDI Joint Venture to reduce the construction period by three months.

For concreting work on the hollow box profile, a construction time of a year was originally planned, and as work started in November 2009, minimum temperatures of up to -25°C were expected during the winter.

To cater for the weather, the contractor planned the temporary protection roof for the construction phase: the possibility of renting the LGS (lattice girder system) protection roof for the period of use provided an economical solution.

Altogether, the jobsite team is using four roof structures: two smaller, permanently installed tents are used for reinforcement work preparations, while two movable protection roofs on basis of the LGS span the formwork and concreting areas.

To ensure unhindered material and concrete installation, the design allows the protection roofs to be moved. The girder supports are equipped with 55.5m long rails, which are over twice as long as the protection roofs and which are easily moved by two to four people. The wheel allows the roofs to be moved in a longitudinal direction.

"At the level of the girder, the static system of a single-span beam with one stationary and one movable support can be realised without any problems by means of system components," says PERI.

The spatial arrangement of the two sets of incremental launching equipment gave the position for the weather protection roofs: the available space between the formwork for both lanes was very limited. Load transfer of the support construction of both weather protection roofs had to be guaranteed via a common central support.

"With Keder track and sheeting, the scaffold constructions result in very light and translucent roofs. The solution in Grudzi?dz also includes a side and gable covering. "Overlapping of the sheeting at all joints ensures a tightly-fitting enclosure which at the same time can easily be opened. With extremely low outside temperatures, the temporary tents were also heated.

"An additional positive effect of the enclosure is the consistently high concrete quality achieved throughout due to the constantly good setting process."

For more information on companies in this article

Related Content

  • A new highway for northern Colombia
    July 17, 2023
    The Pamplona-Cúcuta highway is playing an important role for the development of northern Colombia
  • Ammann pushes the utilisation rate of recycled asphalt even higher
    December 16, 2016
    The Ammann team was confident it had a game-changer on its stand when the 2007 bauma exhibition opened in Munich. The company’s RAH100 asphalt dryer was about to take a massive step forward for the global highway industry – and to lead the market for years to come Ammann’s RAH100 wasn’t a simple upgrade of an existing product. It was much bigger than that. The dryer offered the ability to utilise 100% recycled asphalt … a benefit no other competitor could match. “That 100% utilisation rate was a miles
  • Easing temporary highway danger
    February 22, 2013
    Some of the latest speedometer technology has been successfully trialled in French highway work zones, while tireless work continues across Europe and the United States to reduce the number of work zone deaths and serious injuries involving road workers and motorists. Guy Woodford reports The number of roadworkers being killed and seriously injured on England’s motorways and major trunk roads more than doubled between 2007 and 2010 – from no deaths and 14 serious injuries. This rise has led to to major camp
  • On track with Peri’s new VCT Composite Track
    June 19, 2025

    Building steel composite bridges faster and with higher quality concrete carriageway slabs is possible with PERI’s new VCT Composite Track.

    The system is already being used in Croatia and for construction of the new Thulba viaduct in Germany. Visitors will see a replica of the impressive project in the PERI exhibition hall. The composite track has also been named as a finalist for the bauma innovation award in the construction sector.