Engineering the Saadiyat Expressway

A new bridge, said to be the largest in the United Arab Emirates (UAE) in terms of area, is being constructed as part of a major highway project. The US$550 million Saadiyat Expressway project, which involves Leighton Construction (Abu Dhabi), related to one of Australia's largest contracting groups, in constructing a ten-lane, 6.5km long highway to link the UAE's main city, with an exclusive island lying just offshore.
February 24, 2012 Read time: 4 mins
The Saadiyat Expressway project in Abu Dhabi where RMD Kwikform supplied the formwork and falsework for all the structures
A new bridge, said to be the largest in the United Arab Emirates (UAE) in terms of area, is being constructed as part of a major highway project.

The US$550 million Saadiyat Expressway project, which involves Leighton Construction (Abu Dhabi), related to one of Australia's largest contracting groups, in constructing a ten-lane, 6.5km long highway to link the UAE's main city, with an exclusive island lying just offshore.

Conceived and driven by the Abu Dhabi Tourism Development and Investment Company, the arterial route, together with its interchanges, side roads and 1.6km of bridge decks, is scheduled to be complete in time for the inaugural Abu Dhabi Grand Prix (1 November, 2009), which could well decide the 2009 Formula One World Championship.

In January 319 RMD Kwikform Middle East's engineers started the design process to help contractor Leighton construct the eight in situ concrete box girder bridges and a tunnel required for the expressway.

Leighton Construction (Abu Dhabi) decided to award RMD Kwikform the contract to supply the formwork and falsework for all of the structures on this critical project as a result of the company's reputation and its ability to respond to a complex series of requirements.

These, says RMD, included having the flexibility of service to not only undertake all of the logistical planning and detailed design for each of the different locations, but also to offer the alternative of hire and purchase as appropriate to each application. While the vast majority of the equipment is being sold to Leighton Construction, the formwork for bridge B31 and all the top slab support along the 1.6 km of bridges will be rented.
At 180m long and 80m wide, the Golf Land Bridge will not only be the biggest bridge on the Saadiyat Island Expressway, but also the largest bridge  in terms of area built to date in the UAE.

Andy Teesdale, RMD Kwikform's contract manager for the area, remarks on the size of the project saying: "This is a massive undertaking, where we are working in partnership with Leighton Construction to offer the contractor the level of service essential to keep the reinforced concrete construction for all the structures on track.

"Aside from the fact that the work will see a staggering 215,000m³ of our Rapidshor falsework either purchased or hired to the client, our involvement also involves responsibility for design detailing and site safety. Programming of the work is critical for a lot of reasons, not least the seasonal variation in temperature: because it has such a dramatic effect on the rate at which the concrete hardens and gains strength.

"We normally design for an ambient temperature of 25°C, but this can drop to around 15°C in winter here, which slows the cure and could have potentially disastrous implications if we do not take account of the fact for the formwork design."

The decks to the bridges are all being designed as concrete box girders, with the 2m deep section being divided into a series of cells. The formwork has been planned and detailed so that the main elements can be pre-assembled on the ground, lifted into position and then moved again with as little adjustment as possible.

The most technically challenging requirement for RMD Kwikform to date has been the design and manufacture of special steel forms to cast the complex geometric shapes to a number of the pier heads.

These were fabricated from steel, not to enable high repetitions, but to cope with the very high concrete pressures and variations in profile.

Square on plan, the special shutters measure 2,800mm by 2,600 mm and have a double curvature. The design loading for these special steel forms means only four re-uses as the mix is poured, compacted and hardens.

For the 870m long tunnel that traverses the line of the main highway, once the base slab is laid, RMD Kwikform is to supply its Alform beams and Superslim soldiers to cast the walls. Then for the roof to the tunnel, the method of construction switches to the use of the specialist's table-forms. These will be assembled using RMD Kwikform's Alshor Plus system, making up 30m long sections, which can be struck and advanced as a single unit as soon as the concrete has gained sufficient strength. The cut-and-cover structure will then be backfilled.

Although at 27km², Saadiyat Island is only half the size of Bermuda, but is considered to represent one of the most important development opportunities in Abu Dhabi's history. The completion of the new expressway will help open up this natural idyll as an international tourism destination and residential centre.

For more information on companies in this article

Related Content

  • Overlay extends bridge's life
    July 24, 2012
    More than 3,000 vehicles a day pass over the US-95 Bridge over Lake Creek near the Coeur D'Alene Tribal Casino in Worley, Idaho, USA. The original deck, built in 2007, was poured concrete with a micro-silica layer added for protection. A QTT weather station with FreezeFree anti-icing technology is mounted in the bridge rail. With big variances in temperature and a lot of wind in this region, the original deck material became thick causing a near 80m length of micro-silica to over-harden. Idaho DOT engineers
  • Concrete mixing technology offers advanced recipes
    February 13, 2012
    Modern concrete production plants are using technology to offer more sophisticated mix recipes as Patrick Smith reports. The growing trend towards ever more sophisticated concrete recipes calls for fully developed mixing technology. Companies are responding to the challenges with equipment that offers new levels of sophistication including computer controls and units that can deliver a huge variety of mix recipes.
  • Norway’s long tunnel looks set to beat records
    September 19, 2016
    Norway looks set to retain its position as a leader in tunnelling with the project moving forward to build a new link connecting the city of Stavanger with Bokn. This 27km road tunnel is being designed to carry four lanes of traffic, which would make it the world’s longest underwater road tunnel. It will also be the world’s longest four lane tunnel as well as the world’s deepest road tunnel, dropping around 385-390m below sea level. The Rogaland Fixed Link will form part of the E39 route, connecting Kristia
  • Pilosio Building Peace Awards event attracts high profile speakers
    November 10, 2015
    Actress Sharon Stone challenged guests at the fifth annual awards in Milan to “build me a school”; they accepted. World Highways was there. What does it take to galvanise people into action to help people in need, especially refugees during a time of conflict – as in Syria now? For some it has been the recent media stories – and distressing images – of the child Aylan Kurdi, a three-year old Syrian refugee whose lifeless body lay face down on a beach in Turkey.