Engineering the Saadiyat Expressway

A new bridge, said to be the largest in the United Arab Emirates (UAE) in terms of area, is being constructed as part of a major highway project. The US$550 million Saadiyat Expressway project, which involves Leighton Construction (Abu Dhabi), related to one of Australia's largest contracting groups, in constructing a ten-lane, 6.5km long highway to link the UAE's main city, with an exclusive island lying just offshore.
February 24, 2012 Read time: 4 mins
The Saadiyat Expressway project in Abu Dhabi where RMD Kwikform supplied the formwork and falsework for all the structures
A new bridge, said to be the largest in the United Arab Emirates (UAE) in terms of area, is being constructed as part of a major highway project.

The US$550 million Saadiyat Expressway project, which involves Leighton Construction (Abu Dhabi), related to one of Australia's largest contracting groups, in constructing a ten-lane, 6.5km long highway to link the UAE's main city, with an exclusive island lying just offshore.

Conceived and driven by the Abu Dhabi Tourism Development and Investment Company, the arterial route, together with its interchanges, side roads and 1.6km of bridge decks, is scheduled to be complete in time for the inaugural Abu Dhabi Grand Prix (1 November, 2009), which could well decide the 2009 Formula One World Championship.

In January 319 RMD Kwikform Middle East's engineers started the design process to help contractor Leighton construct the eight in situ concrete box girder bridges and a tunnel required for the expressway.

Leighton Construction (Abu Dhabi) decided to award RMD Kwikform the contract to supply the formwork and falsework for all of the structures on this critical project as a result of the company's reputation and its ability to respond to a complex series of requirements.

These, says RMD, included having the flexibility of service to not only undertake all of the logistical planning and detailed design for each of the different locations, but also to offer the alternative of hire and purchase as appropriate to each application. While the vast majority of the equipment is being sold to Leighton Construction, the formwork for bridge B31 and all the top slab support along the 1.6 km of bridges will be rented.
At 180m long and 80m wide, the Golf Land Bridge will not only be the biggest bridge on the Saadiyat Island Expressway, but also the largest bridge  in terms of area built to date in the UAE.

Andy Teesdale, RMD Kwikform's contract manager for the area, remarks on the size of the project saying: "This is a massive undertaking, where we are working in partnership with Leighton Construction to offer the contractor the level of service essential to keep the reinforced concrete construction for all the structures on track.

"Aside from the fact that the work will see a staggering 215,000m³ of our Rapidshor falsework either purchased or hired to the client, our involvement also involves responsibility for design detailing and site safety. Programming of the work is critical for a lot of reasons, not least the seasonal variation in temperature: because it has such a dramatic effect on the rate at which the concrete hardens and gains strength.

"We normally design for an ambient temperature of 25°C, but this can drop to around 15°C in winter here, which slows the cure and could have potentially disastrous implications if we do not take account of the fact for the formwork design."

The decks to the bridges are all being designed as concrete box girders, with the 2m deep section being divided into a series of cells. The formwork has been planned and detailed so that the main elements can be pre-assembled on the ground, lifted into position and then moved again with as little adjustment as possible.

The most technically challenging requirement for RMD Kwikform to date has been the design and manufacture of special steel forms to cast the complex geometric shapes to a number of the pier heads.

These were fabricated from steel, not to enable high repetitions, but to cope with the very high concrete pressures and variations in profile.

Square on plan, the special shutters measure 2,800mm by 2,600 mm and have a double curvature. The design loading for these special steel forms means only four re-uses as the mix is poured, compacted and hardens.

For the 870m long tunnel that traverses the line of the main highway, once the base slab is laid, RMD Kwikform is to supply its Alform beams and Superslim soldiers to cast the walls. Then for the roof to the tunnel, the method of construction switches to the use of the specialist's table-forms. These will be assembled using RMD Kwikform's Alshor Plus system, making up 30m long sections, which can be struck and advanced as a single unit as soon as the concrete has gained sufficient strength. The cut-and-cover structure will then be backfilled.

Although at 27km², Saadiyat Island is only half the size of Bermuda, but is considered to represent one of the most important development opportunities in Abu Dhabi's history. The completion of the new expressway will help open up this natural idyll as an international tourism destination and residential centre.

For more information on companies in this article

Related Content

  • First deck span completed for Mersey Gateway's north approach viaduct
    February 12, 2016
    The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.
  • JCB excavators and Terex Washing Systems’ plant at work in the Caribbean region
    June 24, 2013
    Excavators and a wash plant have been supplied for work in the Caribbean region. New equipment has been delivered to companies for projects in the countries in the Caribbean. A fleet of eight 20tonne JCB JS200 crawler excavators has been bought by a construction company and put to work in one of the biggest ever highway projects in the Caribbean, while DUO, a Terex Washing Systems’ global distributor, has installed a custom-built Terex sand and gravel wash plant at the Readymix West Indies (W.I.) site in Va
  • Norway’s new ‘green’ highway route
    November 13, 2020
    A new route in Norway will provide a faster and greener highway connection between the capital city Oslo and the northern city of Trondheim
  • Brazil’s Serra do Cafezal Highway
    July 29, 2015
    Brazil's improved Mercosur route will boost capacity and cut travel time - Mauro Nogarin writes. The Régis Bittencourt Highway is one of the main access routes of the Mercosur traffic. It has a length of 400km and connects the main cities of São Paulo and Curitiba, which allows for products to enter from the southeast toward the rest of the southern part of Brazil and later transit to Argentina, Paraguay and Uruguay. Products also flow into Brazil from Mercosur through this major highway. The cost of the hi